# Data Center Construction Statistics 2026: Costs, Pipeline and Delays

US private data center construction ran at a seasonally adjusted annual rate of **$84,950 million** in August 2026, up **73.2%** from **$49,052 million** in August 2025, according to the US Census Bureau. For calendar 2025, the Census Bureau put the value of private data center construction at **$49,737 million**, against **$12,583 million** in 2022.

Those totals count the building and leave out the computers inside it. JLL is forecasting the average global cost will increase **6%** to **$11.3 million** per MW in 2026, and CBRE counted **7,481 megawatts** (MW) under construction in H1 2026 across eight primary North American markets. JLL also says the average wait time for a grid connection in primary data center markets exceeds four years. Each figure below carries its source and date, alongside the wider [data center statistics](/data-center-statistics/).

## Key Takeaways

- Data center construction was about **11.0%** of the **$773,010 million** annual rate for all private nonresidential construction in August 2026, per Census Bureau figures.
- The 2025 data center total of **$49,737 million** was about **3.95** times the 2022 level in the Census annual series.
- The Census Bureau excludes racks or servers in data centers from construction, while JLL says tech fit-out can cost as much as **$25 million** per MW for AI infrastructure.
- JLL’s construction cost figures only include the cost to construct the shell and core, and the average global data center construction cost increased from **$7.7 million** to **$10.7 million** per MW between 2020 and 2025.
- CBRE reports new construction rose **24.8%** across the eight primary North American data center markets in the first half of 2026.
- JLL’s **66 GW** under construction in North America is about **8.8** times CBRE’s **7,481 MW**, because the two firms count different markets.

## Editor’s Choice

- Capacity under construction, North America: JLL reports **66 GW** under construction, **95%** of which is pre-committed.
- Preleased share of CBRE’s pipeline: more than **80%** of all capacity under construction is already preleased, up from **74.3%** a year ago.
- Atlanta under construction: CBRE counts nearly **2,900 MW** under construction, overtaking Northern Virginia.
- Construction cost inflation, 2025: Turner &amp; Townsend finds cost inflation for traditional data centers worldwide averaging **5.5%** in 2025.
- AI construction cost premium: Turner &amp; Townsend identifies a **7-10%** construction cost premium between traditional and AI data centers in the US.
- Permanent debt originations: JLL expects construction activity to drive more than **$700 billion** in permanent debt originations over the next 30 months.

## Data Center Construction Spending by Month

- The Census Bureau put private data center construction at **$84,950 million** in August 2026 (preliminary), up **7.5%** from July 2026 at a seasonally adjusted annual rate.
- That rate equals **$84.95 billion** a year.
- Data center construction in August ran about **37.3%** above the April 2026 rate.
- Total US construction spending was a seasonally adjusted annual rate of **$2,203.1 billion** in August 2026, **1.7%** below the August 2025 estimate.
- Spending on private construction was at a seasonally adjusted annual rate of **$1,655.3 billion** in the same release.
- An annual rate is one month’s spending expressed as a yearly pace, so it is not money spent in that month.

| Month | Private data center construction, annual rate ($ millions) |
|---|---|
| Aug 2025 | 49,052 |
| Apr 2026 | 61,859 |
| May 2026 | 65,688 |
| Jun 2026 (revised) | 72,695 |
| Jul 2026 (revised) | 79,007 |
| Aug 2026 (preliminary) | 84,950 |

*Source: US Census Bureau, Value of Private Construction Put in Place (October 2026)*

### About This Data

- **22** sources on **10** pages: **6** from the US Census Bureau’s construction spending tables, release and definitions, and **16** from CBRE, JLL, Turner &amp; Townsend, and the Uptime Institute.
- Publication window: Turner &amp; Townsend’s 2025-2026 cost index release, JLL’s 2026 Global Data Center Outlook, and **July 2026** to **October 2026** for the rest.
- Selection: government statistics, named real estate and cost consultancies, and an industry survey body; paid market-research report sellers excluded.
- Figures are reviewed on a rolling basis and updated when sources publish new editions.

### How much is being spent on data center construction?

The [Census Bureau](https://www.census.gov/construction/c30/pdf/privsa.pdf) estimates private data center construction at a seasonally adjusted annual rate of **$84,950 million** in August 2026, or **$84.95 billion** a year. The US Census Bureau announced the August 2026 construction statistics on October 1, 2026. The rate is a yearly pace, so it is a measure of momentum. One strong month can mislead; the calendar-year totals show the climb.

## Annual Data Center Construction Spending, 2022 to 2025

- The Census Bureau put private data center construction at **$49,737 million** in 2025, up from **$34,797 million** in 2024, an increase of about **42.9%**.
- The 2025 total was about **3.95** times the **$12,583 million** recorded for 2022.
- Data center construction’s August 2026 annual rate was about **1.71** times the **$49,737 million** calendar-year total for 2025.
- Prior to **2014**, expenditures for data centers were included as part of general office, so the series has no separate history before then.

 PRIVATE DATA CENTER · Source: US Census Bureau, Annual Value of Private Construction Put in Place 2022 to 2025 (2026)   PRIVATE DATA CENTER    US Census Bureau · 2022 to 2025 Private Data Center Construction Spending by Year ($ millions)          50K 37.5K 25K 12.5K 0   12,583 2022  19,995 2023  34,797 2024  49,737 2025    SOURCE US Census Bureau, Annual Value of Private Construction Put in Place 2022 to 2025 (2026)    View the data| Year | $ millions |
|---|---|
| 2022 | 12,583 |
| 2023 | 19,995 |
| 2024 | 34,797 |
| 2025 | 49,737 |





Those totals also say something about every other kind of building.

## Recent Developments

- **October 1, 2026:** The Census Bureau reported construction spending during August 2026 at a seasonally adjusted annual rate of **$2,203.1 billion**, **0.9%** above the revised July estimate.
- **September 8, 2026:** CBRE reported that Northern Virginia remains North America’s largest data center market, adding more than **1 gigawatt** of inventory as vacancy falls to **0.2%**.
- **August 11, 2026:** JLL reported vacancy sustained at **1%** for the third consecutive year despite unprecedented construction activity in North America.
- **July 28, 2026:** The Uptime Institute released the findings of its 16th Annual Global Data Center Survey, which highlights escalating concerns over capacity forecasting, power availability, and supply chain disruptions.
- **First half of 2026:** CBRE found that across North America’s primary markets, net absorption increased by nearly **12%** to **1,456 MW**, while vacancy held steady at **1.4%**.

## Data Center vs Office and Nonresidential Construction

- Data center construction at **$84,950 million** ran at about **1.85** times general office construction of **$45,809 million** in August 2026.
- Private nonresidential construction was **$773,010 million**, down **1.0%** from August 2025, at a seasonally adjusted annual rate.
- Data center construction was about **11.0%** of that nonresidential total in August 2026.
- The office category ran at **$134,119 million**, against **$103,300 million** in August 2025, a rise of about **29.8%**, while general office fell about **9.7%** from **$50,724 million**.
- For calendar 2025, data centers were about **6.3%** of the **$783,741 million** in private nonresidential construction.
- General office construction fell from **$67,662 million** in 2022 to **$51,028 million** in 2025.
- The Census Bureau files data centers under the office category, so the office total rises with them.

 ANNUAL RATE, AUGUST 2026 · Source: US Census Bureau, Value of Private Construction Put in Place (October 2026)   ANNUAL RATE, AUGUST 2026    US Census Bureau · 2026 Private Construction Annual Rate by Type ($ millions)         Data center  84,950 General office  45,809 Lodging  23,328  0 20K 40K 60K 80K 100K   SOURCE US Census Bureau, Value of Private Construction Put in Place (October 2026)    View the data| Construction type | $ millions |
|---|---|
| Data center | 84,950 |
| General office | 45,809 |
| Lodging | 23,328 |





> **By the numbers:** The Census Bureau’s August 2026 table puts data center construction at **$84,950 million** and general office at **$45,809 million**, with private nonresidential construction down **1.0%** from a year earlier. One building type is now carrying the office category while total nonresidential building slips.

That figure is large, and it still leaves out the equipment inside.

## What Census Data Center Construction Spending Counts

- The Census Bureau’s data center category includes buildings that contain the hardware needed for storing, processing, and transmitting digital information.
- Special-purpose equipment, such as racks or servers in data centers, is excluded from construction in the Census definitions.
- Maintenance and repairs to existing structures or service facilities are also excluded from construction.
- JLL notes that tenants are typically responsible for the tech fit-out, which can cost as much as **$25 million** per MW for AI infrastructure.

| Measure | What it covers | What it leaves out | Source |
|---|---|---|---|
| Value of data center construction put in place | Buildings that contain the hardware for storing, processing, and transmitting digital information | Racks or servers; maintenance and repairs | US Census Bureau |
| Average global construction cost per MW | Shell and core | Tenant tech fit-out | JLL |
| Tech fit-out cost for AI infrastructure | as much as $25 million per MW | Shell and core | JLL |

*Source: US Census Bureau construction spending definitions (2026); JLL 2026 Global Data Center Outlook*

### Does Census data center spending include servers?

No. The Census definitions list racks or servers in data centers among special-purpose equipment excluded from construction. The data center category includes buildings that contain the hardware needed for storing, processing, and transmitting digital information, so the series measures the building that holds the servers, and the servers themselves sit outside it. Cost firms price that shell per megawatt.

## Data Center Construction Cost per MW

- JLL reports that data center construction costs have been increasing at a **7%** CAGR between 2020 and 2025, in global averages.
- JLL is forecasting the average global cost will increase **6%** to **$11.3 million** per MW for 2026.
- JLL’s **$11.3 million** global average shell-and-core forecast plus the top of its AI fit-out range, which can cost as much as **$25 million** per MW, comes to about **$36.3 million** per MW.
- JLL says speed to power is the primary criterion driving site selection, followed by community support, latency, and proximity to customers.
- JLL’s averages are global, so a US project can sit above or below them.

 AVERAGE GLOBAL CONSTRUCTION COST · Source: JLL, 2026 Global Data Center Outlook   AVERAGE GLOBAL CONSTRUCTION COST    JLL · 2026 Global Construction Cost per MW ($ millions)          12 9 6 3 0   7.7 2020  10.7 2025  11.3 2026 (forecast)    SOURCE JLL, 2026 Global Data Center Outlook    View the data| Year | $ millions |
|---|---|
| 2020 | 7.7 |
| 2025 | 10.7 |
| 2026 (forecast) | 11.3 |





> **Worth noting:** JLL’s **$11.3 million** per MW is a global average forecast, and JLL notes that its construction cost figures only include the cost to construct the shell and core. Fit-out sits on top of it, and the Census Bureau leaves servers out of its spending series, so neither number describes the full cost of a finished, equipped data center.

### How much does it cost to build a data center per MW?

JLL is forecasting the average global cost will increase **6%** to **$11.3 million** per MW in 2026. The figures only include the cost to construct the shell and core, and tech fit-out can cost as much as **$25 million** per MW for AI infrastructure, so an AI build can cost far more per MW. Per-watt indexes show how far costs vary by market.

## Data Center Construction Cost per Watt by Market

- Turner &amp; Townsend’s analysis of the current cost per watt to build data centers in **52** markets worldwide ranks Tokyo first.
- The same analysis shows cost inflation for traditional data centers worldwide averaging **5.5%** in 2025.
- Tokyo had the highest construction cost per watt at **$15.2**, followed by Singapore at **$14.5**.
- Silicon Valley ranked fifth at **$13.3** per watt and New Jersey sixth at **$12.9**, the two US markets in the top 10.
- Stockholm and Helsinki matched Auckland at **$12.3** per watt, filling places 8 to 10.
- Turner &amp; Townsend identifies a **7-10%** construction cost premium between traditional and AI data centers in the US, comparing projects of similar IT capacity.
- Turner &amp; Townsend’s per-watt index and JLL’s per-MW average use different methods and market sets, so the two series are read side by side and never merged.

 COST PER WATT · Source: Turner &amp; Townsend, Data Centre Construction Cost Index 2025-2026   COST PER WATT    Turner &amp; Townsend · 2025 to 2026 Construction Cost per Watt, Top 8 Markets ($)        Tokyo  $15.2 Singapore  $14.5 Zurich  $14.2 Osaka  $14.1 Silicon Valley  $13.3 New Jersey  $12.9 Oslo  $12.4 Auckland  $12.3  0 4 8 12 16   SOURCE Turner &amp; Townsend, Data Centre Construction Cost Index 2025-2026    View the data| Market | Cost per watt ($) |
|---|---|
| Tokyo | 15.2 |
| Singapore | 14.5 |
| Zurich | 14.2 |
| Osaka | 14.1 |
| Silicon Valley | 13.3 |
| New Jersey | 12.9 |
| Oslo | 12.4 |
| Auckland | 12.3 |





Cost is one constraint; capacity on the ground is the other.

## Data Center Capacity Under Construction in North America

- CBRE reports that the **7,481 megawatts** (MW) under construction in H1 2026 surpassed the previous high reached in 2024.
- More than **80%** of all capacity under construction is already preleased, up from **74.3%** a year ago, per CBRE.
- Less than **1,500 MW** is available for pre-leasing across North America’s primary markets, roughly six months of supply at the current pace of demand, per CBRE.
- CBRE says Atlanta emerged as North America’s most active construction market for the first time, with nearly **2,900 MW** under construction. Those projects are tracked in the [Georgia data center pipeline](https://tricitylocalnews.com/data-centers-in-georgia/).
- JLL finds frontier markets now account for **77%** of all capacity under development.
- JLL also counts **28 GW** of owner-occupied capacity currently under construction by hyperscalers.
- JLL’s **66 GW** under construction in North America is about **8.8** times CBRE’s **7,481 MW**, because CBRE counts only eight primary markets.

| Measure | Scope | Figure | Source |
|---|---|---|---|
| Capacity under construction | Eight primary North American markets, H1 2026 | 7,481 MW | CBRE |
| Capacity under construction | Atlanta, H1 2026 | nearly 2,900 MW | CBRE |
| Share of capacity under construction preleased | Eight primary markets | More than 80% | CBRE |
| Capacity under construction | North America | 66 GW | JLL |
| Share of capacity under construction pre-committed | North America | 95% | JLL |
| Existing and under-construction capacity | Texas | 26 GW | JLL |
| Existing and under-construction capacity | Virginia | 13 GW | JLL |

*Source: CBRE, North American Data Center Trends H1 2026 (September 2026); JLL, North America Data Center Report Midyear 2026 (August 2026)*

### How many megawatts of data centers are under construction?

CBRE counts **7,481 megawatts** (MW) under construction in H1 2026 across eight primary markets, and JLL counts **66 GW** under construction in North America. JLL puts Texas at **26 GW** of existing and under-construction capacity, followed by Virginia at **13 GW**; see the [Texas data center figures](https://tricitylocalnews.com/data-centers-in-texas/) and the [Virginia data center market](https://tricitylocalnews.com/data-centers-in-virginia/). Most of that capacity already has a tenant.

## Who Data Centers Are Being Built For

- JLL says hyperscalers remain the dominant force, accounting for **59%** of 2026 data center tenant demand.
- CBRE reports average asking rents rose for every major deployment size in the first six months of the year, led by an **8.3%** increase for users seeking between **3 MW** and **10 MW** of capacity.
- JLL’s shares do not sum to 100, so the chart shows them as bars. The spending behind the largest tenants sits in the [hyperscale data center statistics](https://tricitylocalnews.com/hyperscale-data-center-statistics/).

 SHARE OF 2026 TENANT DEMAND · Source: JLL, North America Data Center Report Midyear 2026 (August 2026)   SHARE OF 2026 TENANT DEMAND    JLL · 2026 Share of Data Center Tenant Demand by Tenant Type, 2026 (%)         Hyperscalers  59% Neoclouds  11% Pure-play AI companies  7%  0 12 24 36 48 60   SOURCE JLL, North America Data Center Report Midyear 2026 (August 2026)    View the data| Tenant type | Share of 2026 tenant demand (%) |
|---|---|
| Hyperscalers | 59 |
| Neoclouds | 11 |
| Pure-play AI companies | 7 |





Signed tenants do not make power arrive sooner.

## Data Center Construction Delays and Power Constraints

- JLL says data center operators are expected to increase behind-the-meter power arrangements and explore colocated battery storage as the average wait time for a grid connection in primary data center markets exceeds four years.
- In Turner &amp; Townsend’s survey of industry leaders, **48%** said power availability is the most prominent obstacle to delivering projects on schedule.
- CBRE says power-related project delays briefly softened activity at the end of last year, and power constraints are extending completion timelines.
- The Uptime Institute reports that more than half of all respondents in 2026 report difficulties finding qualified candidates for open positions, based on responses from more than **800** data center owners and operators.
- JLL finds that while **79%** of Americans support US leadership in artificial intelligence, only **14%** support data center development in their community.
- The demand side of that power queue is covered in the [data center electricity consumption figures](https://tricitylocalnews.com/data-center-energy-consumption-statistics/).

| Constraint | Figure | Source |
|---|---|---|
| Average wait for a grid connection, primary markets | exceeds four years | JLL |
| Power availability named the top obstacle to on-schedule delivery | 48% of respondents | Turner &amp; Townsend |
| Local supply chains not well prepared for advanced cooling | 83% of respondents | Turner &amp; Townsend |
| Difficulty finding qualified candidates | More than half of respondents | Uptime Institute |
| Support for data center development in their community | 14% of Americans | JLL |

*Source: JLL 2026 Global Data Center Outlook and Midyear 2026 report; Turner &amp; Townsend Data Centre Construction Cost Index 2025-2026; Uptime Institute 2026 Global Data Center Survey*

> **Key finding:** Turner &amp; Townsend’s survey shows it is power and supply chain capacity to deliver these AI data centers, rather than cost, which is raising concern within the sector. With JLL’s grid queue above four years, a project’s start date says less about its finish date than its place in the utility’s connection line.

### Why are data center construction projects delayed?

Power is the most-cited reason. JLL says the average wait time for a grid connection in primary data center markets exceeds four years, and **48%** of Turner &amp; Townsend’s respondents said power availability is the most prominent obstacle to delivering projects on schedule. CBRE adds that power constraints are extending completion timelines. Lenders are pricing the build-out as if those waits will clear.

## Data Center Construction Financing

- Commercial mortgage-backed securities and asset-backed security data center volume combined for **$17 billion** in the first half of 2026, a **29%** increase from the previous year, per JLL.
- Non-credit tenant deals are evaluated ad hoc with spreads approximately **200 to 300** basis points wider than investment-grade hyperscaler construction loans.
- The global data center sector is estimated to grow at a **14%** CAGR over the next five years, according to JLL.

| Measure | Figure | Period | Source |
|---|---|---|---|
| Permanent debt originations driven by construction (forecast) | more than $700 billion | Next 30 months | JLL |
| CMBS and ABS data center volume | $17 billion | First half of 2026 | JLL |
| Investment required for 100 GW of new supply (estimate) | $3 trillion | Through 2030 | JLL |

*Source: JLL, North America Data Center Report Midyear 2026 (August 2026); JLL 2026 Global Data Center Outlook*

## Is data center construction slowing down?

Not on the latest data. The Census Bureau put the August 2026 annual rate up **7.5%** from July and **73.2%** from a year earlier, and CBRE reports new construction rose **24.8%** across the eight primary North American data center markets in the first half of 2026. Grid waits slow individual projects more than the overall pace.

## Conclusion

US private data center construction ran at **$84,950 million** at a seasonally adjusted annual rate in August 2026, up **73.2%** from a year earlier, per the Census Bureau. That number counts the building only, and JLL’s per-MW cost and CBRE’s and JLL’s capacity counts each measure a different slice, so they are read side by side and never added up.

JLL expects the global data center sector to grow at a **14%** CAGR over the next five years. Whether that capacity arrives on time depends on the grid connection queue.