# Data Centers in Virginia Statistics 2026: Power, Taxes and Capacity

Northern Virginia holds **13%** of all reported data center operational capacity globally and **25%** of capacity in the Americas, according to the [Joint Legislative Audit and Review Commission (JLARC)](https://jlarc.virginia.gov/pdfs/reports/Rpt598.pdf) in its 2024 report. Data centers in Virginia occupy approximately **150** data center sites, which collectively house around **340** data center buildings, with over **63 million square feet** of data center space on **7,200 acres** of land (JLARC, 2024).

Dominion Energy reports approximately **54 GW** of capacity under contract against a data center billing peak load of **4.8 GW** as of August 2026. General Assembly money committee staff, using Virginia Tax reports, value the data center sales and use tax exemption at **$673.5 million** in fiscal 2022 and **$1,941.4 million** in fiscal 2025. JLARC’s figures come from its 2024 report, so each one below carries its year.

## Key Takeaways

- Northern Virginia inventory reached **4,496.5 megawatts** in Q2 2026, according to CBRE, while JLL counts nearly **7 GW** of inventory in Northern Virginia, so the market’s size depends on who measures it.
- Data center operators reported a **188%** increase in the reported sales tax exemption benefit from FY 22-25, and JLARC put the state portion of the exempted amount at an estimated **$683 million** in FY23.
- Virginia’s 2026 budget language imposes a data center electricity consumption tax at a rate of **$0.011/kWh** in FY 2027 and FY 2028, depositing no more than **$600.0 million** of the revenue to the general fund.
- Dominion Energy leaves **19 GW** (**59%**) of Engineering Letters of Authorization (ELOAs) excluded from the forecast, and its industry average ramp period is **5** years, maturing at a utilization rate of **63%**.
- Loudoun County budgets **$879,094,354** in computer equipment taxes on data centers, up from **$581,550,433** in FY 2023, and says the growth of data center personal property tax revenues will plateau in the next five to **10** years.
- Commercial electricity sales in Virginia increased by nearly **30.0 million megawatt-hours (MWh)** between 2019 and 2025, growth largely driven by a concentration of data centers, according to the EIA.

## Editor’s Choice

- Data center buildings in Virginia: around **340**, across approximately **150** data center sites.
- Northern Virginia share of Americas capacity: **25%** of capacity in the Americas.
- Northern Virginia net absorption, Q2 2026: **467.7 MW**, driving vacancy down to **0.2%**.
- Dominion data center metered accounts: approximately **500**, with **55** data center companies connected, per Dominion Energy.
- Jobs the data center industry supports across Virginia’s economy, annual average: approximately **74,000** jobs, based on average spending by the industry between FY21 and FY23.
- Water used by Virginia data centers, 2023: an estimated **2.1 billion gallons**.

## Data Centers in Virginia by the Numbers

- Virginia’s data center sites vary in size, ranging from a single **2,400**-square-foot data center building to a campus of seven buildings that total more than **3 million square feet**.
- Northern Virginia accounts for **13%** of all reported data center operational capacity globally and **25%** of capacity in the Americas (JLARC, 2024).
- Loudoun County’s economic development department reports **53.3 million square feet** of data centers currently in operation or under development.
- Loudoun’s data centers are home to more than **3,500** technology companies.
- There has not been a single day without data center construction in Loudoun in more than **15** years, according to the county.

| Measure | Figure | Source and year |
|---|---|---|
| Data center sites in Virginia | approximately 150 | JLARC, 2024 |
| Data center buildings in Virginia | around 340 | JLARC, 2024 |
| Data center space in Virginia (sq ft) | over 63 million | JLARC, 2024 |
| Land used by Virginia data centers (acres) | 7,200 | JLARC, 2024 |
| Share of industry in Loudoun, Prince William and Fairfax | 80% | JLARC, 2024 |
| Northern Virginia share of global operational capacity | 13% | JLARC, 2024 |
| Northern Virginia share of Americas capacity | 25% | JLARC, 2024 |
| Loudoun data center space in operation or under development (sq ft) | 53.3 million | Loudoun County, 2026 |

*Source: JLARC, Data Centers in Virginia 2024; Loudoun County Department of Economic Development, 2026*

### About This Data

- **13** sources: **6** from Virginia legislative staff, Loudoun County and the US Energy Information Administration, **3** company disclosures from Dominion Energy and Digital Realty, **2** commercial real estate research releases from CBRE and JLL, and **2** news reports.
- Publication window: JLARC’s **2024** report to **October 2026**.
- Selection: government, utility, company and named research publishers only; market-research report sellers excluded.
- JLARC figures are older than 12 months, so each one carries its data year in the text.
- Figures are reviewed on a rolling basis and updated when sources publish new editions.

### How many data centers are in Virginia?

JLARC counted approximately **150** data center sites in Virginia, which collectively house around **340** data center buildings in its 2024 report. Loudoun County alone accounts for approximately half of the state’s data center industry in terms of number of sites, building square footage, and estimated energy usage. Building counts change quickly, so the JLARC total is a 2024 snapshot. Those counts measure buildings and floor space; megawatts tell a different story.

## Northern Virginia Data Center Capacity by Market

- CBRE reports that Northern Virginia remained the country’s largest market by inventory, with **4,496.5 MW** in Q2 2026.
- Northern Virginia’s inventory is about **2.5** times Atlanta’s **1,803.2 MW**.
- JLL says Northern Virginia maintained its position as the world’s largest single data center market with nearly **7 GW** of inventory despite vacancy tightening to less than **1%**.
- JLL ranks Texas first for existing and under-construction capacity, at **26 GW**, ahead of Virginia.
- JLARC’s 2024 report also calls Northern Virginia the largest data center market in the world.

 INVENTORY · Source: CBRE Research, Q2 2026   INVENTORY    CBRE Research · Q2 2026 Data Center Inventory by Market, Q2 2026 (MW)         Northern Virginia  4,496.5 Atlanta  1,803.2 Dallas-Fort Worth  1,432.8 Phoenix  1,069.2 Chicago  910.6 Silicon Valley  509.2 Hillsboro, OR  491.4 New York/Tri-State  190.0  0 1K 2K 3K 4K 5K   SOURCE CBRE Research, Q2 2026    View the data| Market | Value (MW) |
|---|---|
| Northern Virginia | 4,496.5 |
| Atlanta | 1,803.2 |
| Dallas-Fort Worth | 1,432.8 |
| Phoenix | 1,069.2 |
| Chicago | 910.6 |
| Silicon Valley | 509.2 |
| Hillsboro, OR | 491.4 |
| New York/Tri-State | 190.0 |





CBRE and JLL track inventory in named metro markets, while JLARC’s share uses reported operational capacity worldwide, so the three figures measure different things. Northern Virginia ranks first on all three measures: CBRE’s inventory, JLL’s inventory and JLARC’s share of operational capacity. Our [ranking of the largest data centers in the US](https://tricitylocalnews.com/largest-data-centers-us/) covers the individual facilities.

> **Worth noting:** CBRE counts Northern Virginia inventory at **4,496.5 MW** and JLL counts nearly **7 GW** of inventory, while JLARC’s **13%** share covers all reported data center operational capacity globally. Each publisher defines the market and its inventory differently, so the gap reflects scope.

| Measure | Figure | Scope | Source |
|---|---|---|---|
| Northern Virginia inventory | 4,496.5 MW | Single market, Q2 2026 | CBRE |
| Northern Virginia inventory | nearly 7 GW | Single market, H1 2026 | JLL |
| Virginia capacity | 13 GW | Existing and under construction, H1 2026 | JLL |
| Northern Virginia share of global capacity | 13% | Reported operational capacity | JLARC, 2024 |
| Data center capacity under contract | approximately 54 GW | Engineering and Construction Letters of Authorization (ELOA, CLOA) and Electric Service Agreements (ESA) | Dominion Energy, 2026 |

*Source: CBRE Research, Q2 2026; JLL, H1 2026; JLARC, 2024; Dominion Energy, 2026*

## Recent Developments

- **September 29, 2026:** Dominion Energy presented its data center forecast to PJM, listing **32,473 MW** of Engineering Letters of Authorization (ELOA), with **13,429 MW** in forecast (**41%**).
- **August 19, 2026:** Virginia General Assembly money committee staff presented an overview of the consumption tax, which deposits no more than **$600.0 million** of the revenue to the general fund, with excess revenue refunded on a pro rata basis to each payer.
- **August 11, 2026:** JLL reported that North America now has **66 GW** under construction, **95%** of which is pre-committed.
- **August 2026:** The State Corporation Commission directed utilities such as Dominion Energy to develop tariffs requiring data centers to cover the full cost of transmission lines and grid upgrades that serve only their operations, WSET reported.
- **July 23, 2026:** Digital Realty reported a **64%** stake in three fully leased data centers in Northern Virginia containing **288 megawatts** of IT capacity, at a gross value of approximately **$7.8 billion**.

## Data Center Alley and Where Virginia’s Data Centers Are

- **80%** of Virginia’s data center industry is concentrated in three Northern Virginia localities: Loudoun, Prince William, and Fairfax, according to JLARC (2024).
- Loudoun County says much of the world’s internet traffic passes through Loudoun’s digital infrastructure, known as “Data Center Alley”.
- Data centers and the data center ecosystem provide more than **17,000** jobs in Loudoun County.
- Dominion Energy says data center load increases are occurring in northern Virginia, the Stafford area, Richmond, and Southside VA.
- JLARC’s 2024 report finds significant new market growth is expected in counties outside of Northern Virginia and along the I-95 corridor to Central Virginia.

### Why are so many data centers in Virginia?

JLARC’s 2024 report attributes Northern Virginia’s market prominence to a strong fiber network, supply of reliable, cheap energy, available land, proximity to major national customers, and the creation of a state data center tax incentive. Of those factors, the tax incentive is the one the General Assembly controls directly, which is why its cost now appears in state budget reviews.

## Virginia Data Center Construction and Leasing

- CBRE reports that Atlanta emerged as North America’s most active construction market for the first time, with nearly **2,900 MW** under construction, overtaking Northern Virginia.
- Northern Virginia had **10.8 MW** available, against **39.6 MW** in Dallas-Fort Worth, in CBRE’s Q2 2026 count.
- CBRE says Northern Virginia recorded the highest level of net absorption, **467.7 MW**, driving vacancy down to **0.2%** in Q2 2026.
- Loudoun County issued building permits for **9.8 million square feet** of data center space in 2025.
- Digital Realty says the Northern Virginia stake transaction listed under Recent Developments reflects an expected initial stabilized cap rate of over **6.5%**, with the newly developed assets expected to be fully stabilized in the first half of 2027 and the first half of 2028.

 AVAILABLE CAPACITY · Source: CBRE Research, Q2 2026   AVAILABLE CAPACITY    CBRE Research · Q2 2026 Available Data Center Capacity by Market, Q2 2026 (MW)         Dallas-Fort Worth  39.6 Atlanta  29.5 Silicon Valley  21.2 Chicago  20.0 New York/Tri-State  13.7 Phoenix  12.1 Northern Virginia  10.8 Hillsboro, OR  1.1  0 8 16 24 32 40   SOURCE CBRE Research, Q2 2026    View the data| Market | Value (MW) |
|---|---|
| Dallas-Fort Worth | 39.6 |
| Atlanta | 29.5 |
| Silicon Valley | 21.2 |
| Chicago | 20.0 |
| New York/Tri-State | 13.7 |
| Phoenix | 12.1 |
| Northern Virginia | 10.8 |
| Hillsboro, OR | 1.1 |





Virginia’s pipeline is one part of the wider [US data center construction pipeline](https://tricitylocalnews.com/data-center-construction-statistics/), where CBRE now places Atlanta ahead on megawatts under construction.

## Dominion Energy Data Center Contracts and Load

- Dominion Energy reports approximately **54 GW** of capacity under contract (ELOA, CLOA, ESA), and over **13** years of experience serving data centers.
- Dominion counts approximately **500** data center metered accounts and **55** data center companies connected.
- The largest contract stage is **32,473 MW** of Engineering Letters of Authorization (ELOA).
- Firm contracts, the CLOA and ESA stages combined, total **21,353 MW**.
- Dominion says data center billing peak load as of August 2026 is **4.8 GW**, and says its market is mainly cloud/AI inference.
- The utility’s IRP answers state that the majority (approximately **85%**) of the increase in the load forecast over the next 20 years is from data centers.

 CAPACITY UNDER CONTRACT · Source: Dominion Energy, presentation to PJM, September 2026   CAPACITY UNDER CONTRACT    Dominion Energy · 2026 Dominion Data Center Capacity Under Contract by Stage (MW)         ELOA  32,473 ESA  11,997 CLOA  9,356  0 7K 14K 21K 28K 35K   SOURCE Dominion Energy, presentation to PJM, September 2026    View the data| Contract stage | Value (MW) |
|---|---|
| ELOA | 32,473 |
| ESA | 11,997 |
| CLOA | 9,356 |





- The three contract stages add up to **53,826 MW**.
- Of the ELOA block, **19,044 MW** are not in forecast (**59%**).
- Dominion’s industry average ramp period is **5** years, maturing at a utilization rate of **63%**, so contracted capacity runs well above the load it eventually draws.

 SHARE OF ELOA CAPACITY · Source: Dominion Energy, presentation to PJM, September 2026    SHARE OF ELOA CAPACITY    Dominion Energy · 2026 Dominion ELOA Capacity In and Out of Its Forecast (%)     59% NOT IN FORECAST    Not in forecast 59%    In forecast 41%     SOURCE Dominion Energy, presentation to PJM, September 2026    View the data| ELOA capacity | Value (%) |
|---|---|
| Not in forecast | 59% |
| In forecast | 41% |





### How much electricity do Virginia data centers use?

Dominion Energy reports a data center billing peak load of **4.8 GW** as of August 2026. Statewide, commercial electricity sales in Virginia increased by nearly **30.0 million MWh** between 2019 and 2025, growth the [U.S. Energy Information Administration](https://www.eia.gov/todayinenergy/detail.php?id=67664) says is largely driven by a concentration of data centers. Contracted megawatts are a promise; the grid’s peaks show what has already arrived.

## Virginia Electricity Demand From Data Centers

- Virginia’s commercial sales from 2019 to 2025 showed much faster growth than in any other state except Texas, a much larger state, per the EIA.
- The growth in sales of electricity in Virginia is largely driven by a concentration of data centers, as well as electric vehicle adoption and building electrification.
- Summer peak load in PJM’s Dominion zone was **23,905 MW** in 2025, **23%** higher than in 2019.
- Winter peak load in PJM’s Dominion zone was **25,413 MW** in the 2025-26 winter season, **45%** higher than in the 2019-20 winter season.
- PJM expects peak summer load will grow at an average of **5.4%** per year over the next **10** years, a downward revision from the **6.3%** it projected in its 2025 forecast.
- An independent forecast commissioned by JLARC for its 2024 report shows that unconstrained demand for power in Virginia would double within the next **10** years, with the data center industry being the main driver.
- JLARC’s independent forecast largely matches the most recent forecast by PJM.

> **By the numbers:** Winter peak load in PJM’s Dominion zone was **25,413 MW** in the 2025-26 winter season, **45%** higher than in the 2019-20 winter season, per the EIA, while the summer peak of **23,905 MW** in 2025 was **23%** higher than in 2019. Winter now sets the higher bar for the zone.

The same load growth shows up in national [data center energy consumption statistics](https://tricitylocalnews.com/data-center-energy-consumption-statistics/), where Virginia’s grid is one regional input.

## Data Centers and Virginia Electric Bills

- JLARC staff estimated in 2024 that a typical residential customer with monthly consumption of **1,000 kWh** could experience generation- and transmission-related costs increasing by an estimated **$33** per month by 2040 under the unconstrained demand scenario.
- Under the half of unconstrained demand scenario, which is still difficult to achieve, the total cost is estimated to increase by around **$14** per month (JLARC, 2024).
- JLARC concluded in 2024 that building enough infrastructure to meet unconstrained demand would be very difficult.
- Gov. Abigail Spanberger says Virginia electric customers should not bear the cost of infrastructure built exclusively to serve data centers.
- WSET reported that the State Corporation Commission decision could save ratepayers hundreds of millions of dollars.

## Virginia Data Center Sales Tax Exemption Cost

- Virginia Tax data put the data center sales tax exemption value at **$1,941.4 million** in fiscal 2025, up from **$903.5 million** in fiscal 2023.
- The fiscal 2025 value is about **2.9** times the fiscal 2022 value.
- JLARC reports that data centers and tenants reported saving **$928.6 million** in sales taxes in FY23 because of the exemption, including state, local, and regional portions of the tax.
- JLARC’s 2024 report calls the exemption by far the state’s largest economic development incentive, with the next closest incentive valued at **$74 million**.
- Exemption value includes **1%** sales tax for localities and the additional amounts collected in some localities, such as Northern Virginia and the Historic Triangle.

 EXEMPTION VALUE · Source: Virginia Tax data via Virginia General Assembly money committee staff, August 2026   EXEMPTION VALUE    Virginia Tax · 2026 Virginia Data Center Sales Tax Exemption ($ millions)          2K 1.5K 1K 500 0   673.5 2022  903.5 2023  1,292.5 2024  1,941.4 2025    SOURCE Virginia Tax data via Virginia General Assembly money committee staff, August 2026    View the data| Fiscal year | $ millions |
|---|---|
| 2022 | 673.5 |
| 2023 | 903.5 |
| 2024 | 1,292.5 |
| 2025 | 1,941.4 |





The Virginia Tax series and JLARC’s savings figure both rest on what operators reported, but they differ in FY23 value (**$903.5 million** against **$928.6 million**) and in scope, so the two are shown separately and never merged.

> **Key finding:** From FY 22-25, data center operators reported a **188%** increase in the reported sales tax exemption benefit, according to General Assembly money committee staff, and JLARC estimated the state portion of the exempted amount at **$683 million** in FY23. Each new qualifying building adds to the exemption’s cost.

## Virginia Data Center Electricity Consumption Tax

- Virginia’s 2026 budget imposes a data center electricity consumption tax at a rate of **$0.011/kWh** on all electricity consumed at each data center per month in FY 2027 and FY 2028.
- Revenue above the general fund deposit is refunded on a pro rata basis to each payer after the close of the fiscal year.
- To qualify for the sales tax exemption, a data center operator must make at least a **$150.0 million** capital investment and create **50** new jobs paying at least **1.5** times the prevailing local average wage.
- The sales tax exemption is set to expire **July 1, 2035**.

| Provision | Terms |
|---|---|
| Consumption tax rate | $0.011 per kWh |
| Fiscal years taxed | FY 2027 and FY 2028 |
| General fund deposit cap | no more than $600.0 million |
| Exemption: capital investment | at least $150.0 million |
| Exemption: new jobs | 50, paying at least 1.5 times the local average wage |
| Distressed locality: capital investment | at least $70.0 million |
| Distressed locality: new jobs | ten |
| Exemption expiry | July 1, 2035 |

*Source: Virginia General Assembly money committee staff, 2026 budget overview, August 2026*

## Loudoun County Data Center Tax Revenue

- Loudoun County’s FY 2027 adopted budget shows computer equipment taxes on data centers of **$879,094,354**.
- That is about **51%** above the **$581,550,433** collected in FY 2023.
- The same budget lists real property taxes for data centers of **$417,666,456**, because starting with the FY 2027 Budget, real property taxes attributable to data centers are shown as a different component of real property revenue.
- The assessed value of taxable commercial and industrial property that existed on January 1, 2025 jumped dramatically by **26.36%** during 2025, with data centers seeing the largest increases year-over-year.

 COMPUTER EQUIPMENT TAX ON DATA · Source: Loudoun County, FY 2027 Adopted Budget, General Fund Revenue   COMPUTER EQUIPMENT TAX ON DATA    Loudoun County · 2027 Loudoun Computer Equipment Tax on Data Centers ($)          1B 750M 500M 250M 0   $581,550,433 FY 2023  $684,787,341 FY 2024  $699,818,945 FY 2025  $794,780,452 FY 2026  $879,094,354 FY 2027    SOURCE Loudoun County, FY 2027 Adopted Budget, General Fund Revenue    View the data| Fiscal year | Value ($) |
|---|---|
| FY 2023 | $581,550,433 |
| FY 2024 | $684,787,341 |
| FY 2025 | $699,818,945 |
| FY 2026 | $794,780,452 |
| FY 2027 | $879,094,354 |





> **Why it matters:** Loudoun County warns that the growth of data center personal property tax revenues will plateau in the next five to **10** years at some future point, so the county must limit the growth in its budget to a level that is sustainable over time. The county is planning for that ceiling while the revenue is still rising.

### Do data centers pay taxes in Virginia?

Yes. Locally, Loudoun County’s FY 2027 adopted budget counts **$879,094,354** in computer equipment taxes on data centers and **$417,666,456** in real property taxes for data centers. At the state level, data centers and tenants reported saving **$928.6 million** in sales taxes in FY23 because of the exemption. The 2026 state budget also imposes a data center electricity consumption tax at a rate of **$0.011/kWh** on all electricity consumed at each data center per month in FY 2027 and FY 2028.

## Loudoun County Tax Rates and Data Centers

- Loudoun County says the general personal property tax rate, which applies to property in data centers, remains the same as the current rate for tax years 2026 and 2027: **$4.15** per $100 in assessed value.
- The real property rate fell about **29.7%** between tax year 2016 and tax year 2026.
- The vehicle personal property rate cut for tax year 2026 equals about **25.5%**.
- While the Board of Supervisors has consistently lowered the real property tax rates, homeowners’ individual tax bills have varied due to increased property values.

| Rate | Per $100 of assessed value ($) |
|---|---|
| Real property, tax year 2016 | 1.145 |
| Real property, tax year 2026 | 0.805 |
| Vehicle personal property, prior rate | 4.15 |
| Vehicle personal property, tax year 2026 | 3.09 |
| Vehicle personal property, tax year 2027 (planned) | 2.94 |
| General personal property including data centers, tax years 2026 and 2027 | 4.15 |

*Source: Loudoun County, Data Centers: Tax Revenues and County Budget, 2026*

## Virginia Data Center Jobs and Economic Impact

- JLARC’s 2024 report estimates the data center industry provides approximately **74,000** jobs, **$5.5 billion** in labor income, and **$9.1 billion** in Virginia GDP overall to the state economy annually.
- These estimates are just over **1%** of total statewide employment, income, and Virginia GDP during the last three years (JLARC, 2024).
- The construction phase accounts for **59,000** jobs (**35,000** direct), the largest share of the total.
- The model credits construction with **$4.3 billion** in labor income and **$6.4 billion** in Virginia GDP, against **$1.2 billion** and **$2.7 billion** for the operations phase.
- The figures come from a Weldon Cooper Center economic impact analysis of the data center industry impacts, based on data center spending between FY21 and FY23 reported to VEDP.

 Total jobs vs Direct jobs · Source: JLARC, Data Centers in Virginia 2024 (Weldon Cooper Center analysis of FY21 to FY23 spending)      JLARC · 2024 Virginia Data Center Jobs by Phase, FY21 to FY23 (jobs) Total jobs vs Direct jobs    Total jobs  Direct jobs          80K 64K 48K 32K 16K 0   59,000  35,000  15,000  4,400  74,000  39,400   Construction Operations Total  Total jobs · 59,000 Direct jobs · 35,000 Total jobs · 15,000 Direct jobs · 4,400 Total jobs · 74,000 Direct jobs · 39,400   SOURCE JLARC, Data Centers in Virginia 2024 (Weldon Cooper Center analysis of FY21 to FY23 spending)    View the data| Phase | Total jobs | Direct jobs |
|---|---|---|
| Construction | 59,000 | 35,000 |
| Operations | 15,000 | 4,400 |
| Total | 74,000 | 39,400 |







Construction supplies most of the [data center jobs](https://tricitylocalnews.com/data-center-jobs-statistics/) in JLARC’s model, which ties the total to how fast new buildings go up. Loudoun’s ecosystem job count uses a different scope, so the two figures are not added together.

## Virginia Data Center Water Use

- In 2023, the data center industry used an estimated **2.1 billion gallons** of water, according to JLARC.
- One building used **243 million gallons** (**10%** of the industry’s total use).
- Most data centers use about the same amount of water (or less) as an average large office building (**6.7 million gallons** per year), and some require less than a typical household.

| Water measure, 2023 | Figure |
|---|---|
| Industry water use | an estimated 2.1 billion gallons |
| Share from reclaimed water | just over a third |
| Share of total state withdrawals | less than 0.5% |
| Buildings using over 50 million gallons each | 11 |
| One building’s use | 243 million gallons |
| Average large office building, per year | 6.7 million gallons |

*Source: JLARC, Data Centers in Virginia 2024*

JLARC presents its 2023 [data center water use](https://tricitylocalnews.com/data-center-water-usage-statistics/) total as an estimate based on available data, so the industry figure is approximate, not an exact count.

## Prince William Digital Gateway and Community Opposition

- WTOP reported that at full buildout, the Digital Gateway would have been the largest data center campus in the world, with over **22 million square feet** of data centers spread out across **2,000 acres** along Pageland Lane adjacent to Manassas National Battlefield Park.
- The Prince William Board of County Supervisors approved the rezoning for the controversial campus in December 2023.
- Prince William Circuit Court Judge Kimberly Irving ruled the rezonings were void due to improper public notice ahead of the county’s **27**-hour hearing and eventual vote on the matter.
- There were two primary lawsuits challenging the project, one involving the Oak Valley Homeowners Association and another from the American Battlefield Trust.
- The two cases were heard together on appeal, and the state Court of Appeals upheld the August 2025 ruling on **March 31, 2026**.

## Conclusion

Virginia data centers give Northern Virginia **13%** of all reported data center operational capacity globally, and the state’s sales tax exemption reached **$1,941.4 million** in fiscal 2025. The capacity, the utility contracts, Loudoun’s equipment tax and the new consumption tax all scale with the same buildings, which is why the [data center statistics](https://tricitylocalnews.com/data-center-statistics/) for Virginia now read as much like budget and grid figures as real estate counts.

PJM expects peak summer load will grow at an average of **5.4%** per year over the next **10** years, the consumption tax applies in FY 2027 and FY 2028, and the sales tax exemption is set to expire **July 1, 2035**. Those dates mark when the next set of Virginia figures will show whether the tax and tariff changes slowed the build-out.