# Largest Data Centers in the US Statistics 2026: Sites and Capacity

The United States has more than **3,000** operational data centers. More than **1,500** new data centers are in various stages of development nationwide, according to a Pew Research Center analysis of Data Center Map data. The largest known AI data center by IT power is Colossus 2 in Memphis, TN, drawing **946 MW**, per Epoch AI. Which of the largest data centers in the US comes first depends on the yardstick: IT power, compute, floor space, site count, or an operator’s own planned capacity.

Virginia lists **685** data centers, compared with **466** in Texas. On capacity, JLL puts Texas at **26 GW** of existing and under-construction capacity, followed by Virginia at **13 GW**. Meta says its Richland Parish data center in Louisiana will deliver over **2 GW** of compute capacity, and Vantage lists its Frontier campus in Shackelford County, Texas, at **1.4 GW** of critical IT load.

## Key Takeaways

- More than **3,000** US data centers are operational, and more than **1,500** are in development, per Data Center Map data current as of Feb. 19, 2026.
- Colossus 2 in Memphis, TN, is the largest known AI data center by IT power at **946 MW**, ahead of Anthropic-Amazon New Carlisle at **910 MW**.
- Virginia leads the state count with **685** data centers, while JLL’s capacity figures put Texas first at **26 GW** of existing and under-construction capacity.
- **67%** of planned data centers are in rural areas, while **87%** of existing data centers are in urban ones.
- CBRE counts **4,496.5 MW** of Northern Virginia inventory, while JLL describes nearly **7 GW** of inventory in the same market.
- Atlanta has nearly **2,900 MW** under construction, overtaking Northern Virginia as North America’s most active construction market.

## Editor’s Choice

- Louisiana AI campus: over **2 GW** of compute capacity at Meta’s Richland Parish data center.
- Pennsylvania campus: a new **2 GW** data center campus in Shippingport, Pennsylvania, spanning three facilities.
- West Texas mega-campus: **1.4 GW** of critical IT capacity across **10** single-story data centers spanning more than **3.7 million square feet**.
- Stargate planned capacity: nearly **7 GW** and over **$400 billion** in investment over the three years following OpenAI’s 2025 announcement.
- North American pipeline: **66 GW** under construction, **95%** of which is pre-committed, per JLL.
- Wisconsin AI campus: **1.2 million square feet** under roofs across three buildings at Microsoft’s Fairwater data center.

## Largest Data Centers in the US by Power Capacity

- Epoch AI names Colossus 2, owned by SpaceXAI (xAI) in Memphis, TN, as the largest known AI data center by IT power, drawing **946 MW**.
- Colossus 2 leads Anthropic-Amazon New Carlisle, the second site on Epoch AI’s IT power list, by just **36 MW**.
- Individual AI sites in Epoch AI’s coverage range from under **50 MW**, enough to power a small city like Albany, NY, to over **1000 MW**.
- Meta says Richland Parish will deliver over **2 GW** of compute capacity to train future open-source large language models.
- Epoch AI projects **2.0 GW** for OpenAI’s Stargate site in Shackelford County, Texas, where construction began in Q3 2025. Vantage’s figure for its Frontier campus in the same county is critical IT load, so the two numbers measure different things.

| Campus | Location | Capacity | What the figure measures | Counted by |
|---|---|---|---|---|
| Colossus 2 | Memphis, TN | 946 MW | IT power | Epoch AI |
| Anthropic-Amazon New Carlisle | New Carlisle, IN | 910 MW | IT power | Epoch AI |
| Microsoft Fairwater Atlanta | Fayetteville, GA | 636 MW | IT power | Epoch AI |
| Meta Prometheus | New Albany, OH | 471 MW | IT power | Epoch AI |
| Richland Parish | Louisiana | over 2 GW | Planned compute capacity | Meta |
| Project Phoenix | Shippingport, Pennsylvania | 2 GW | Campus capacity | Aligned Data Centers |
| Frontier (Stargate Shackelford County site) | Shackelford County, Texas | 2.0 GW; 1.4 GW | Projected capacity (Epoch AI); critical IT load (Vantage) | Epoch AI; Vantage Data Centers |
| El Paso campus | El Paso, Texas | 1 GW | Planned compute capacity | Meta |

*Source: Epoch AI, Meta, Aligned Data Centers, Vantage Data Centers, 2025 to 2026*

### About This Data

- Compiled from 14 publications: Pew Research Center, CBRE, JLL, two Epoch AI data pages, and nine operator pages and announcements.
- Sources date from 2024 (xAI’s Colossus page, covering 2024 to February 2025) to October 2026 (Epoch AI’s hub update).
- Only research centers, market trackers, and operators’ own pages qualified; paid market-research reports were excluded. Operator figures are labeled as company claims, and Epoch AI figures are attributed to Epoch AI.
- Figures are reviewed on a rolling basis and updated when sources publish new editions.

### What is the largest data center in the US?

By IT power, the largest known AI data center is Colossus 2 in Memphis, TN, drawing **946 MW**, according to Epoch AI. By an operator’s own planned figure, Meta calls Richland Parish its largest data center yet, with over **2 GW** of compute capacity. A ranking that does not name its metric cannot settle the question.

## Largest AI Data Centers by Compute

- Colossus 2 is also the largest AI data center by compute, with **1,112,000** H100-equivalents, per Epoch AI.
- Colossus 2 carries about **1.4 times** the compute of Microsoft Fairwater Atlanta.
- Anthropic-Amazon New Carlisle ranks second by IT power at **910 MW** but sits behind Microsoft Fairwater Atlanta on compute, at **686,000** H100-equivalents against **769,000**.
- xAI says Colossus was built in **122 days**, then doubled in **92 days** to **200,000** H100 GPUs in a single interconnected cluster.
- Amazon says Project Rainier features nearly half a million Trainium2 chips and is now fully operational.
- Company chip counts and Epoch AI’s H100-equivalent estimates use different units, so they do not belong in one ranking of the [AI data center build-out](https://tricitylocalnews.com/ai-data-centers/).

 COMPUTE · Source: Epoch AI, October 2026   COMPUTE    Epoch AI · 2026 Largest US AI Data Centers by Compute (H100-Equivalents)         Colossus 2, Memphis  1,112,000 Microsoft Fairwater Atlanta  769,000 Anthropic-Amazon New Carlisle  686,000 Google Pryor (North)  637,000 Meta Prometheus  536,000 OpenAI Stargate Abilene  509,000  0 300K 600K 900K 1.2M 1.5M   SOURCE Epoch AI, October 2026    View the data| AI data center | H100-Equivalents |
|---|---|
| Colossus 2, Memphis | 1,112,000 |
| Microsoft Fairwater Atlanta | 769,000 |
| Anthropic-Amazon New Carlisle | 686,000 |
| Google Pryor (North) | 637,000 |
| Meta Prometheus | 536,000 |
| OpenAI Stargate Abilene | 509,000 |





## Recent Developments

- **October 12, 2026:** Epoch AI’s update puts the combined IT power capacity of the **94** AI data centers it covers at **14.1 GW**, or **18.3 GW** of capacity once cooling and other overhead are included.
- **September 10, 2026:** Aligned Data Centers broke ground on [Project Phoenix](https://aligneddc.com/press-release/project-phoenix-data-center-shippingport-pa/), a new **2 GW** data center campus in Shippingport, Pennsylvania, that will support an estimated **3,000** construction jobs.
- **August 11, 2026:** JLL reported that North America data center demand reached an all-time high of **25 GW** of absorption in the first half of 2026, double the level from a year ago.
- **July 28, 2026:** Meta announced a venture with BlackRock for an El Paso, Texas campus with **1 GW** of compute capacity, expected to begin bringing capacity online in **2028**.
- **H1 2026:** Atlanta emerged as North America’s most active construction market for the first time, with nearly **2,900 MW** under construction, per CBRE.

## How Many Data Centers Are in the US

- Data Center Map, one of the oldest and most comprehensive industry databases, lists more than **3,000** operational US data centers, with figures current as of Feb. 19, 2026.
- The planned category includes data centers listed as under construction, planned, or land banked.
- **67%** of planned data centers are in rural areas, while **87%** of existing data centers are in urban areas.
- **39%** of planned data centers are in counties that currently don’t have any.
- **38%** of Americans live within **5 miles** of at least one operational data center, and **42%** live close to an existing or planned one.
- The United States has the most large-scale AI data centers in Epoch AI’s coverage. National [data center capacity, capex, and outage figures](https://tricitylocalnews.com/data-center-statistics/) sit behind that count.

 Urban vs Rural · Source: Pew Research Center analysis of Data Center Map, February 2026      Pew Research Center · 2026 US Data Centers by Area Type and Status (%) Urban vs Rural          100% 75% 50% 25% 0%    33% Planned   87% Currently operating    Urban (%)  Rural (%)  Urban (%) · 33% Rural (%) · 67% Urban (%) · 87% Rural (%) · 13%   SOURCE Pew Research Center analysis of Data Center Map, February 2026    View the data| Status | Urban (%) | Rural (%) |
|---|---|---|
| Planned | 33% | 67% |
| Currently operating | 87% | 13% |





> **Key finding:** Pew Research Center’s analysis of Data Center Map listings finds that **67%** of planned US data centers are in rural areas, while **87%** of existing ones are urban. **39%** of planned sites are in counties that currently don’t have any. About two in five planned sites are heading to counties with no data center today.

### How many data centers are in the US?

The United States has more than **3,000** operational data centers, according to Pew Research Center’s analysis of Data Center Map. More than **1,500** more are in various stages of development, in data current as of Feb. 19, 2026. Planned sites include those listed as under construction, planned, or land banked.

## Data Centers by State

- Virginia has **685** data centers in total, **398** currently operating and **287** planned. The [Virginia data center figures](https://tricitylocalnews.com/data-centers-in-virginia/) break that state total down further.
- Virginia lists **1.5 times** as many data centers as Texas.
- JLL says Texas has cemented its position as the state for data centers, with **26 GW** of existing and under-construction capacity. The figures on [data centers in Texas](https://tricitylocalnews.com/data-centers-in-texas/) add the state’s grid queue and tax data.
- The top eight states hold **2,540** data centers between them.
- California ranks third by total with **331**, of which **277** are currently operating.

 DATA CENTERS · Source: Pew Research Center analysis of Data Center Map, February 2026   DATA CENTERS    Pew Research Center · 2026 US Data Centers by State, Top 8 (Count)         Virginia  685 Texas  466 California  331 Illinois  262 Georgia  235 Ohio  223 Arizona  184 New York  154  0 140 280 420 560 700   SOURCE Pew Research Center analysis of Data Center Map, February 2026    View the data| State | Count |
|---|---|
| Virginia | 685 |
| Texas | 466 |
| California | 331 |
| Illinois | 262 |
| Georgia | 235 |
| Ohio | 223 |
| Arizona | 184 |
| New York | 154 |





### Which state has the most data centers?

Virginia has the most data centers, with **685** listed in total, followed by Texas with **466** and California with **331**. On capacity, the order flips: JLL puts Texas at **26 GW** of existing and under-construction capacity, followed by Virginia at **13 GW**. Count rewards many smaller sites; capacity rewards a few very large ones.

## Planned vs Operating Data Centers by State

- Virginia and Texas have the most planned data centers, at **287** and **170**, and the most currently operating, at **398** and **296**.
- Georgia lists **141** planned data centers against **94** currently operating. The [Georgia data center pipeline](https://tricitylocalnews.com/data-centers-in-georgia/) shows planned sites outrunning built ones.
- Georgia’s planned sites outnumber its operating ones by **47**.
- Indiana lists **54** planned data centers against **38** currently operating.
- New York has **148** operating data centers and only **6** planned, while Florida has **120** operating and **8** planned.

 Currently operating vs Planned · Source: Pew Research Center analysis of Data Center Map, February 2026      Pew Research Center · 2026 Operating vs Planned Data Centers by State (Count) Currently operating vs Planned    Currently operating  Planned          400 320 240 160 80 0   398  287  296  170  139  123  98  86  94  141  38  54   Virginia Texas Illinois Arizona Georgia Indiana  Currently operating · 398 Planned · 287 Currently operating · 296 Planned · 170 Currently operating · 139 Planned · 123 Currently operating · 98 Planned · 86 Currently operating · 94 Planned · 141 Currently operating · 38 Planned · 54   SOURCE Pew Research Center analysis of Data Center Map, February 2026    View the data| State | Currently operating | Planned |
|---|---|---|
| Virginia | 398 | 287 |
| Texas | 296 | 170 |
| Illinois | 139 | 123 |
| Arizona | 98 | 86 |
| Georgia | 94 | 141 |
| Indiana | 38 | 54 |







## States With the Most Data Center Capacity

- Texas has **26 GW** of existing and under-construction capacity, followed by Virginia at **13 GW**, according to JLL.
- Texas holds **2 times** Virginia’s capacity on JLL’s measure.
- Frontier markets now account for **77%** of all capacity under development.
- JLL names West Texas, Ohio, Louisiana and the Carolinas as energy-rich, build-friendly markets that have drawn heavy investment in recent years. The [Ohio data center figures](https://tricitylocalnews.com/data-centers-in-ohio/) show how one of those frontier states is building out.
- Epoch AI’s coverage of large-scale AI data centers is concentrated in Texas, with **14** sites covered.

 AI DATA CENTER SITES COVERED · Source: Epoch AI, October 2026   AI DATA CENTER SITES COVERED    Epoch AI · 2026 Large AI Data Centers Covered by Epoch AI, by State (Sites)         Texas  14 Ohio  7 Virginia  7 Nebraska  4 Iowa  4  0 3 6 9 12 15   SOURCE Epoch AI, October 2026    View the data| State | Sites |
|---|---|
| Texas | 14 |
| Ohio | 7 |
| Virginia | 7 |
| Nebraska | 4 |
| Iowa | 4 |





> **Why it matters:** Pew Research Center’s count puts Virginia ahead with **685** data centers to **466** in Texas, while JLL’s capacity figures put Texas at **26 GW** of existing and under-construction capacity, followed by Virginia at **13 GW**. A buyer or analyst comparing states has to pick the measure first, because site counts and gigawatts point to different leaders.

## Largest Data Center Markets by Inventory

- Northern Virginia remained the country’s largest market by inventory at **4,496.5 MW**, recording the highest level of net absorption (**467.7 MW**) and driving vacancy down to **0.2%**, per CBRE Research.
- Northern Virginia’s inventory is **2.5 times** that of Atlanta.
- Total data center supply across North America’s primary markets grew **33.7%** year over year, while vacancy held steady at **1.4%**.
- CBRE’s eight primary North American data center markets are Northern Virginia, Dallas-Fort Worth, Silicon Valley, Chicago, Phoenix, New York Tri-State, Atlanta and Hillsboro.

 INVENTORY · Source: CBRE Research, Q2 2026   INVENTORY    CBRE Research · Q2 2026 Data Center Inventory by Primary Market, Q2 2026 (MW)         Northern Virginia  4,496.5 Atlanta  1,803.2 Dallas-Fort Worth  1,432.8 Phoenix  1,069.2 Chicago  910.6 Silicon Valley  509.2 Hillsboro, OR  491.4 New York/Tri-State  190.0  0 1K 2K 3K 4K 5K   SOURCE CBRE Research, Q2 2026    View the data| Market | Value (MW) |
|---|---|
| Northern Virginia | 4,496.5 |
| Atlanta | 1,803.2 |
| Dallas-Fort Worth | 1,432.8 |
| Phoenix | 1,069.2 |
| Chicago | 910.6 |
| Silicon Valley | 509.2 |
| Hillsboro, OR | 491.4 |
| New York/Tri-State | 190.0 |





> **Worth noting:** CBRE puts Northern Virginia’s inventory at **4,496.5 MW**, while JLL calls it the world’s largest single data center market with nearly **7 GW** of inventory. Both firms agree on the leader but report different totals.

### What is the largest data center market in the US?

Northern Virginia remained the country’s largest market by inventory, at **4,496.5 MW** in CBRE Research’s Q2 2026 data, with vacancy down to **0.2%**. JLL describes it as the world’s largest single data center market, with nearly **7 GW** of inventory.

## Top Data Center Markets by Absorption and Construction

- The **7,481 MW** under construction across the eight primary markets in H1 2026 surpassed the previous high reached in 2024, with new construction up **24.8%**.
- In CBRE’s eight primary markets, more than **80%** of all capacity under construction is already preleased, up from **74.3%** a year ago.
- Across North America as a whole, JLL counts **66 GW** under construction, **95%** of which is pre-committed.
- Atlanta hit record absorption of **918 MW** in just six months. Wider [data center construction figures](https://tricitylocalnews.com/data-center-construction-statistics/) track the same build cycle nationally.
- Columbus compressed to **0.1%** vacancy despite bringing significant new supply online.

| Market | H1 2026 figure | What it measures | Counted by |
|---|---|---|---|
| Atlanta | nearly 2,900 MW | Under construction | CBRE |
| Atlanta | 918 MW | Absorbed in six months | JLL |
| Dallas-Fort Worth | over 2 GW | Delivered | JLL |
| Austin/San Antonio | 1.7 GW | Completed | JLL |
| Austin/San Antonio | 796 MW | Absorbed | JLL |
| Phoenix | 1.7 GW | Under construction | JLL |
| Phoenix | 442 MW | Absorbed | JLL |
| Columbus | 0.1% | Vacancy | JLL |

*Source: CBRE Research, JLL, H1 2026*

## Largest Data Center Campuses by Floor Space

- Meta’s Richland Parish campus covers four million square feet and will house Hyperion, its largest multi-gigawatt AI training cluster.
- Meta’s Richland Parish campus is **3.3 times** the square footage under roofs at Microsoft’s Fairwater data center in Wisconsin.
- Microsoft says constructing Fairwater required **46.6 miles** of deep foundation piles and **26.5 million pounds** of structural steel.
- Meta has contracted more than **$875 million** with Louisiana businesses in the year to December 2025.

| Campus | Location | Floor space | Site details | Counted by |
|---|---|---|---|---|
| Richland Parish | Louisiana | four million square feet | Houses the Hyperion AI training cluster | Meta |
| Frontier | Shackelford County, Texas | more than 3.7 million square feet | 1,200 acres, 10 data centers | Vantage Data Centers |
| Fairwater | Wisconsin | 1.2 million square feet under roofs | 315 acres, three buildings | Microsoft |

*Source: Meta, Vantage Data Centers, Microsoft, 2025 to 2026*

## Gigawatt Data Center Campuses Under Construction

- Stargate has seven locations across the US, all now showing active development, which together add up to over **9 GW** of planned capacity, by Epoch AI’s estimate.
- The most advanced site, in Abilene, Texas, is already operating at an estimated **0.3 GW**.
- Epoch AI projects a high of **2.2 GW** for Doña Ana County, New Mexico, and under **0.3 GW** for Lordstown, Ohio, the smallest projection among the seven sites.
- OpenAI says Stargate reached nearly **7 GW** of planned capacity with five new US sites. OpenAI’s total is a company announcement, and Epoch AI’s is an outside estimate, so the two should not be merged.
- OpenAI ties that planned capacity to over **$400 billion** in investment over the three years following its 2025 announcement.
- Meta’s El Paso campus represents an investment of over **$10 billion** and will support more than **4,000** construction jobs at peak.

 PROJECTED CAPACITY · Source: Epoch AI, April 2026   PROJECTED CAPACITY    Epoch AI · 2026 Stargate Sites by Projected Capacity, Epoch AI Estimate (GW)         Doña Ana County, NM  2.2 Shackelford County, TX  2.0 Saline Township, MI  1.4 Port Washington, WI  1.3 Abilene, TX  1.2 Milam County, TX  1.2  0 0.5 1 1.5 2 2.5   SOURCE Epoch AI, April 2026    View the data| Stargate site | Value (GW) |
|---|---|
| Doña Ana County, NM | 2.2 |
| Shackelford County, TX | 2.0 |
| Saline Township, MI | 1.4 |
| Port Washington, WI | 1.3 |
| Abilene, TX | 1.2 |
| Milam County, TX | 1.2 |





## Where New Data Centers Are Being Built

- Three-quarters of all planned data centers will be built in the South and Midwest, with the South alone accounting for nearly half of them (**48%**).
- The South has **754** planned data centers and **1,209** existing ones, a **62%** increase from its current total.
- The Northeast has **106** planned data centers and **397** existing ones, a **26%** increase.
- Nine-in-ten data centers are within **5 miles** of another one.
- Epoch AI notes that, among the large-scale AI data centers it covers, many new sites are clustered near major power infrastructure and fiber networks in the American Midwest and South. Access to power ties the siting map closely to [data center electricity use](https://tricitylocalnews.com/data-center-energy-consumption-statistics/).

 Source: Pew Research Center analysis of Data Center Map, February 2026      Pew Research Center · 2026 Existing vs Planned Data Centers by US Region (Count)    Existing  Planned          1.5K 1.2K 900 600 300 0   1,209  754  807  277  655  419  397  106   South West Midwest Northeast  Existing · 1,209 Planned · 754 Existing · 807 Planned · 277 Existing · 655 Planned · 419 Existing · 397 Planned · 106   SOURCE Pew Research Center analysis of Data Center Map, February 2026    View the data| Region | Existing | Planned |
|---|---|---|
| South | 1,209 | 754 |
| West | 807 | 277 |
| Midwest | 655 | 419 |
| Northeast | 397 | 106 |







## Who Uses the Largest Data Centers

- Hyperscalers account for **59%** of 2026 data center tenant demand, with **28 GW** of owner-occupied capacity currently under construction, per JLL.
- JLL says the demand mix is diversifying rapidly as neoclouds mature into a meaningful component.
- Microsoft says its global Microsoft Cloud spans over **400** data centers in **70** regions. Operator-by-operator footprints appear in the [data center companies by size](https://tricitylocalnews.com/largest-data-center-companies/).
- The flagship Stargate campus in Abilene, Texas, is already up and running on Oracle Cloud Infrastructure (OCI). Hyperscale site totals are covered in the [hyperscale data center counts](https://tricitylocalnews.com/hyperscale-data-center-statistics/).

| Tenant group | Share of 2026 North American demand |
|---|---|
| Hyperscalers | 59% |
| Neoclouds | 11% |
| Pure-play AI companies | 7% |

*Source: JLL, August 2026*

## Conclusion

The United States has more than **3,000** operational data centers and more than **1,500** in development, per Pew Research Center’s analysis of Data Center Map. Colossus 2 tops Epoch AI’s IT power list at **946 MW**. Leadership among the largest data centers in the US changes with the measure: Virginia on site count, Texas on capacity, Northern Virginia on metro inventory, and the operator-announced gigawatt campuses on planned size.

JLL counts **66 GW** under construction across North America, and **67%** of planned US sites are rural. Until an independent tracker measures them, each operator’s planned gigawatts remain a company claim.