CBRE counted 7,481 MW of data center capacity under construction across eight primary North American markets in the first half of 2026. More than 80% of it was already preleased. Vacancy in those markets held at 1.4%. JLL counts 66 GW under construction across North America, 95% of it pre-committed. These data center statistics cover construction, vacancy, footprint, spending and outages, each with its source and date.
Amazon, Alphabet and Microsoft spent a combined $134,934 million on property and equipment in the quarter ended June 30, 2026. Uptime Institute reports that outage frequency on a per-site basis declined for a fifth consecutive year, yet 1 in 5 respondents reported costs exceeding $1 million for their most recent major outage.
Key Takeaways
- CBRE tracks 7,481 MW under construction in eight primary North American markets, while JLL counts 66 GW under construction across North America, with frontier markets holding 77% of all capacity under development.
- More than 80% of the capacity under construction in CBRE’s primary markets is preleased, up from 74.3% a year ago, leaving less than 1,500 MW available for pre-leasing.
- Data center projects made up 63.3% of US private office construction spending in August 2026, at a seasonally adjusted annual rate of $84,950 million.
- Data center vacancy in North America held at 1% for the third consecutive year, per JLL, and 95% of the capacity under construction is pre-committed.
- 57% of respondents to Uptime’s 2025 annual survey said their most recent major outage cost more than $100,000.
- Texas has 26 GW of existing and under-construction capacity, followed by Virginia at 13 GW, according to JLL.
Editor’s Choice
- North America absorption: 25 GW absorbed in the first half of 2026, double the level from a year ago.
- AWS footprint: 124 Availability Zones within 39 Geographic Regions.
- Digital Realty footprint: 300+ facilities in 55+ metros across 30+ countries.
- Alphabet capex: $44,924 million in purchases of property and equipment in the quarter ended June 30, 2026.
- Meta 2026 capex outlook: $130 billion to $145 billion, including principal payments on finance leases.
- Publicly reported outages: 122 collected by Uptime in 2025.
Data Center Statistics: Construction Pipeline in North America
- The 7,481 MW under construction in CBRE’s eight primary markets in H1 2026 surpassed the previous high reached in 2024.
- New construction rose 24.8% in the first half of 2026, after power-related project delays briefly softened activity at the end of last year.
- Less than 1,500 MW remains available for pre-leasing, roughly six months of supply at the current pace of demand.
- Total data center supply across North America’s primary markets grew 33.7% year over year.
- Atlanta became North America’s most active construction market for the first time, with nearly 2,900 MW under construction, overtaking Northern Virginia.
- Northern Virginia remained the largest market by inventory, at 4,496.5 MW.
- JLL’s 66 GW North American figure is about 8.8 times CBRE’s eight-market total.
| Market | Inventory (MW) |
|---|---|
| Northern Virginia | 4,496.5 |
| Atlanta | 1,803.2 |
| Dallas-Fort Worth | 1,432.8 |
| Phoenix | 1,069.2 |
| Chicago | 910.6 |
| Silicon Valley | 509.2 |
| Hillsboro, OR | 491.4 |
| New York/Tri-State | 190.0 |
Source: CBRE Research, Q2 2026
Worth noting: CBRE’s 7,481 MW covers eight primary markets: Northern Virginia, Dallas-Fort Worth, Silicon Valley, Chicago, Phoenix, New York, Atlanta and Hillsboro. JLL’s 66 GW spans North America, where frontier markets account for 77% of all capacity under development. The two totals are far apart, and each firm states its own coverage, so read each figure against that coverage.
About This Data
- Compiled from 15 publications: 5 company earnings releases, 1 cloud provider infrastructure page, 2 US government releases and 1 national laboratory report, 4 Uptime Institute publications, and research releases from CBRE and JLL.
- Sources date from December 2024 to October 2026, with Census Bureau construction data through August 2026 and the AWS infrastructure page as captured in October 2026.
- Only company filings, company infrastructure pages, government data, and independent research qualified; paid market-research reports were excluded.
- Figures are reviewed on a rolling basis and updated when sources publish new editions.
Data Center Vacancy, Rents and Financing
- Net absorption across CBRE’s primary markets increased by nearly 12% to 1,456 MW.
- Among CBRE’s eight primary markets, Northern Virginia recorded the highest net absorption, 467.7 MW, driving its vacancy down to 0.2%. JLL measures absorption differently, so its Atlanta figure in the Top Markets table below is not directly comparable.
- Dallas-Fort Worth had 39.6 MW of available capacity, against 1.1 MW in Hillsboro, OR.
- Average asking rents rose for every major deployment size, led by an 8.3% increase for users seeking between 3 MW and 10 MW.
- JLL says data center rental rates have increased nearly 70% since 2020, with rent growth averaging 9% annually.
- JLL expects construction to drive more than $700 billion in permanent debt originations over the next 30 months.
- Commercial mortgage-backed securities and asset-backed security data center volume combined for $17 billion in the first half of 2026, a 29% increase from the previous year.
View the data
| Market | Value |
|---|---|
| Dallas-Fort Worth | 39.6 |
| Atlanta | 29.5 |
| Silicon Valley | 21.2 |
| Chicago | 20.0 |
| New York/Tri-State | 13.7 |
| Phoenix | 12.1 |
| Northern Virginia | 10.8 |
| Hillsboro, OR | 1.1 |
What is the data center vacancy rate?
JLL puts data center vacancy in North America at 1%, the third consecutive year at that level. CBRE measured 1.4% across its eight primary markets in the first half of 2026, steady with year-end 2025. The two firms track different market sets, so each rate reads against its own scope. JLL expects current pricing momentum to hold through 2030.
Recent Developments
- August 27, 2026: CBRE reported that construction in eight primary North American markets rose 24.8% to 7,481 MW in the first half of 2026, with more than 80% of it preleased.
- August 11, 2026: JLL reported record North America absorption of 25 GW in the first half of 2026, double the level from a year ago.
- July 28, 2026: Uptime Institute released its 16th Annual Global Data Center Survey, with responses from more than 800 data center owners and operators.
- July 23, 2026: Digital Realty reported second-quarter bookings expected to generate $208 million of annualized GAAP rental revenue at its share, and a $1.4 billion backlog of signed-but-not-commenced leases at its share.
Cloud and Colocation Footprint
- The AWS Cloud spans 124 Availability Zones within 39 Geographic Regions, with announced plans for 7 more Availability Zones and 2 more Regions in Saudi Arabia and Chile.
- AWS defines an Availability Zone as one or more discrete data centers with redundant power, networking, and connectivity in an AWS Region.
- The AWS Cloud in North America has 31 Availability Zones within 9 Geographic Regions, the physical layer under much of cloud computing adoption in the region.
- Digital Realty reports a global data center footprint of 300+ facilities in 55+ metros across 30+ countries on six continents.
- Digital Realty acquired a stake in three fully leased data centers in Northern Virginia containing 288 megawatts of IT capacity, at a gross value of approximately $7.8 billion.
- For the first time, third-party data center facilities and services account for a larger share of IT workloads than enterprise-owned data centers, by facility rather than total capacity, according to Uptime Institute.
| Operator | Measure | Value |
|---|---|---|
| AWS | Availability Zones worldwide | 124 |
| AWS | Geographic Regions worldwide | 39 |
| AWS | Availability Zones in North America | 31 |
| AWS | Geographic Regions in North America | 9 |
| Digital Realty | Data center facilities | 300+ |
| Digital Realty | Metros | 55+ |
| Digital Realty | Countries | 30+ |
Source: Amazon Web Services, October 2026; Digital Realty, July 2026
How many data centers are there?
None of the sources here give a single worldwide count of data centers, so operator footprints and megawatt totals are the clearest public measures. Digital Realty reports 300+ facilities in 55+ metros. AWS runs 124 Availability Zones, and each one is one or more discrete data centers.
Top Data Center Markets
- Texas has 26 GW of existing and under-construction capacity, followed by Virginia at 13 GW.
- Frontier markets now account for 77% of all capacity under development in North America.
- Dallas-Fort Worth delivered over 2 GW while absorbing even more.
- Columbus compressed to 0.1% vacancy, and Atlanta hit record absorption of 918 MW in six months.
- JLL found that 79% of Americans support US leadership in artificial intelligence, but only 14% support data center development in their community, a 65-point support gap.
| Market metric | Value | Source |
|---|---|---|
| Texas existing and under-construction capacity | 26 GW | JLL |
| Virginia existing and under-construction capacity | 13 GW | JLL |
| Frontier markets’ share of capacity under development | 77% | JLL |
| Atlanta absorption, H1 2026 | 918 MW | JLL |
| Columbus vacancy | 0.1% | JLL |
| Northern Virginia net absorption, H1 2026 | 467.7 MW | CBRE |
| Northern Virginia vacancy | 0.2% | CBRE |
Source: JLL, CBRE Research, 2026
US Data Center Construction Spending
- US private data center construction ran at a seasonally adjusted annual rate of $84,950 million in August 2026, per the Census Bureau’s preliminary estimate.
- That rate was up 7.5% from July 2026 and 73.2% from August 2025.
- The annual rate rose 37.3% between April and August 2026.
- General office construction ran at $45,809 million, and the full office category at $134,119 million.
- Data centers accounted for 5.1% of the $1,655,280 million annual rate for all private construction.
View the data
Why it matters: Census Bureau data puts US data center construction at an $84,950 million annual rate in August 2026, while general office building ran at $45,809 million. Data center projects now carry the office category, so a rising office construction total is mostly a data center story.
Hyperscaler Capital Expenditure Statistics
- Amazon’s purchases of property and equipment reached $54,208 million in the three months ended June 30, 2026, up from $32,183 million a year earlier.
- Alphabet’s purchases of property and equipment rose to $44,924 million in the quarter, from $22,446 million a year earlier.
- Microsoft’s additions to property and equipment were $35,802 million in the quarter, against $17,079 million a year earlier.
- Microsoft’s additions totaled $115,948 million for the twelve months ended June 30, 2026, up from $64,551 million.
- Meta reported second-quarter 2026 capital expenditures, including principal payments on finance leases, of $31.08 billion.
- Meta narrowed its 2026 capital expenditure outlook to $130 billion to $145 billion, from $125 billion to $145 billion.
- The four companies define capex differently: Meta includes finance-lease principal, while the others report cash purchases or additions of property and equipment.
View the data
Big Tech Capex Trend by Quarter
- Amazon’s trailing-twelve-month purchases of property and equipment, net of proceeds from sales and incentives, reached $169,007 million in Q2 2026, up 64% year over year.
- Amazon’s purchases for the six months ended June 30, 2026 totaled $98,411 million, against $57,202 million a year earlier.
View the data
| Quarter | Value |
|---|---|
| Q1 2025 | 87,978 |
| Q2 2025 | 102,953 |
| Q3 2025 | 115,903 |
| Q4 2025 | 128,320 |
| Q1 2026 | 147,299 |
| Q2 2026 | 169,007 |
- Alphabet’s quarterly purchases of property and equipment climbed from $23,953 million in Q3 2025 to $27,851 million in Q4 2025, $35,674 million in Q1 2026 and $44,924 million in Q2 2026.
- Alphabet’s trailing-twelve-month purchases reached $132,402 million, and its Q2 2026 free cash flow was negative $5,855 million.
View the data
Data Center Outage Statistics
- Uptime Institute collected details of 122 publicly reported outages in 2025.
- Uptime has tracked 1,009 publicly reported outages from 2016 to 2025, with a peak of 165 in 2019.
- The proportion of publicly reported outages that were severe decreased to 7% in 2025, down five percentage points from 2024.
- In Uptime’s 2025 survey (n=754), 10% of organizations that reported an impactful outage in the past three years classified their most impactful one as serious or severe, compared with 9% in 2024.
- Among organizations with an impactful outage in the past three years, 39% rated the most impactful one negligible and 3% rated it severe.
- Third-party IT and data center service providers, including cloud and internet giants, telecommunications and colocation companies, accounted for about two-thirds of publicly reported outages over nine years of tracking.
View the data
Key finding: Uptime Institute finds outage rates on a per-site basis declining for the fifth consecutive year, but 57% of respondents to its 2025 survey said their most recent major outage cost more than $100,000, and 1 in 5 reported costs exceeding $1 million. Per site, outages are less frequent, but the major ones that do occur remain expensive.
Causes of Data Center Outages
- Networking and connectivity problems were the most common cause of IT service outages over the past three years, named by 23% of respondents.
- Power was named by 21%, and IT systems or software by 18%.
- Nearly one in five respondents report having no IT service outages in the past three years, an improvement of nine percentage points over 2024.
- Outages linked to fiber and connectivity issues are rising and more likely to result in extended disruptions.
- Power issues accounted for 45% of respondents’ most recent impactful data center outages in 2025, down from 54% in 2024.
- Among power-related outages, respondents most often cited UPS failure (39%), transfer switch failure (34%), and generator failure (28%).
View the data
What causes most data center outages?
Power remains the leading cause of impactful outages, according to Uptime Institute, and failures involving UPS systems, transfer switches, and generators are dominant. Across IT services more broadly, network-related outages continue to be the most frequently reported cause of IT service disruptions. Uptime adds that worsening grid constraints and high-density workloads are introducing new pressure points.
Data Center Resiliency and Workforce Statistics
- Monitoring and analytics was rated the most effective resiliency investment of the past three years by 53% of operators, and 48% will increase it in 2026.
- Uptime says investment is shifting toward automation and controls, which 36% rated effective and 42% will increase in 2026.
- More than half of all respondents in 2026 report difficulties finding qualified candidates for open positions.
- A growing number of operators now report peak rack densities of 30 kW or higher.
- Uptime’s 2026 survey drew more than 800 owners and operators, and 52% of them are located in North America and Europe.
View the data
Data Center Energy and Water Use
- Lawrence Berkeley National Laboratory’s report for the Department of Energy projects that data centers will consume approximately 6.7 to 12% of total US electricity by 2028.
- Hyperscale and colocation facilities accounted for 84% of the 66 billion liters of direct water use in 2023, while internal data centers fell to 12%.
- Hyperscale data centers are expected to consume between 60 and 124 billion liters of water in 2028.
- PUE trends, grid pressure, and AI demand projections sit on the data center energy consumption statistics page.
| Measure | 2014 | 2023 | 2028 projection |
|---|---|---|---|
| US data center electricity use | 58 TWh | 176 TWh | 325 to 580 TWh |
| Share of total US electricity | Not stated | About 4.4% | About 6.7 to 12% |
| US data center direct water use | 21.2 billion liters | 66 billion liters | Not stated |
Source: Lawrence Berkeley National Laboratory, US Department of Energy, December 2024
Conclusion
CBRE tracks 7,481 MW under construction in North America’s eight primary markets, with vacancy at 1.4%. JLL counts 66 GW under construction across North America. New capacity is being leased about as fast as it is built, and the hyperscalers’ own filings show spending still climbing quarter after quarter.
CBRE says power constraints are extending completion timelines even as more projects move from the planning stage into construction, while Uptime Institute says the pace of improvement in per-site outage frequency has slowed. Power, approvals, and community acceptance, more than demand, now look like the limits on how fast that capacity arrives.