The 94 AI data centers Epoch AI covers have a combined 14.1 GW of IT power capacity. Total facility power pushes their footprint to 18.3 GW, more than New York City’s peak demand of 11 GW. Epoch AI ranks Colossus 2, owned by SpaceXAI (xAI) in Memphis, first by IT power at 946 MW and first by compute at 1,112,000 H100-equivalents.
Stargate’s seven US sites add up to over 9 GW of planned capacity, while Abilene, Texas, already operates at an estimated 0.3 GW, per Epoch AI’s April 2026 report. OpenAI’s chip-supply agreements with NVIDIA, AMD and Broadcom cover at least 26 GW. Epoch AI’s figures are estimates, not disclosed specifications, and set beside company announcements, they show how far signed capacity runs ahead of capacity in service.
Key Takeaways
- OpenAI’s NVIDIA, AMD and Broadcom agreements cover at least 26 GW of capacity, against 14.1 GW of IT power across the 94 sites Epoch AI covers.
- OpenAI said its five new sites, the Abilene flagship and its CoreWeave projects, brought Stargate to nearly 7 gigawatts of planned capacity, on a path to its 10-gigawatt commitment; Epoch AI’s April 2026 count of the seven US sites is over 9 GW.
- The record for the largest AI data center by computing capacity has doubled every seven months since Colossus 1 launched in August 2024.
- About 80% of the time, an Epoch AI IT power estimate falls within a factor of 1.4 of the true value.
- Total computing capacity from AI chips has grown by approximately 3.3x per year since 2022, and NVIDIA AI chips account for over 60% of total compute.
- The IEA says global investment in data centers nearly doubled since 2022 to half a trillion dollars in 2024.
Editor’s Choice
- Largest AI data center by IT power: Colossus 2 in Memphis, at 946 MW, per Epoch AI.
- Compute in Epoch AI’s coverage: 14.6 million H100-equivalents across 94 sites.
- Stargate investment plan: $500 billion over the next four years, with $100 billion deployed immediately.
- Meta Richland Parish Data Center: $50 billion-plus data center investment in Louisiana, per Meta.
- Claude on Trainium2: more than 1 million Trainium2 chips, per Amazon.
- NVIDIA Data Center revenue: $89.0 billion in the second quarter ended July 26, 2026, up 117% from a year ago.
Largest AI Data Centers by Power Capacity
- Colossus 2, owned by SpaceXAI in Memphis, TN, is the largest known AI data center by IT power, drawing 946 MW.
- Anthropic-Amazon New Carlisle, owned by Amazon, follows at 910 MW.
- Epoch AI’s threshold for inclusion is roughly 100 MW of IT power at full buildout.
- Individual sites range from under 50 MW to over 1,000 MW.
- Average power consumption is typically 60 to 80% of capacity, due to idle time and maintenance.
- The rankings show power capacity, not actual power draw.
- Epoch AI says about 80% of the time, an IT power estimate falls within a factor of 1.4 of the true value, so individual figures are approximate.
| Site | Location | IT power (MW) |
|---|---|---|
| Colossus 2 (SpaceXAI) | Memphis, TN | 946 |
| Anthropic-Amazon New Carlisle | New Carlisle, IN | 910 |
| Microsoft Fairwater Atlanta | Fayetteville, GA | 636 |
| DayOne Nusajaya | Johor Bahru, Malaysia | 473 |
| Meta Prometheus | New Albany, OH | 471 |
Source: Epoch AI (October 2026)
About This Data
- Compiled from 25 sources: 7 Epoch AI research pages, 12 company announcements and site pages, 4 quarterly earnings releases, 1 utility release, and 1 International Energy Agency report.
- Sources were published between January 2025 and October 2026.
- Only primary and independent sources qualify; no paid market-research reports are used.
- Epoch AI figures are modeled estimates, and chip counts from companies are their own statements. Figures are reviewed on a rolling basis and updated when sources publish new editions.
What is an AI data center?
Epoch AI defines an AI data center as a collection of one or more buildings located near each other, with a shared hardware owner or facility operator, that run hardware specialized for AI, such as GPUs or custom chips like Google’s TPUs. These sites may be used to experiment on, train, and deploy AI models.
What is the largest AI data center in the world?
Colossus 2, owned by SpaceXAI in Memphis, TN, is the largest known AI data center by both IT power, at 946 MW, and compute, at 1,112,000 H100-equivalents, according to Epoch AI. Epoch AI’s research suggests no data center will have meaningfully greater capacity than Colossus 2 until the second half of 2027. General-purpose campuses, ranked by footprint rather than AI compute, appear in the largest US data center campuses.
Largest AI Data Centers by Compute
- Colossus 2 leads by compute at 1,112,000 H100-equivalents.
- The 94 sites in Epoch AI’s coverage hold a combined 14.6 million H100-equivalents.
- Colossus 2 holds about 1.45 times the compute of second-ranked Microsoft Fairwater Atlanta.
- Microsoft Fairwater Atlanta holds 769,000 H100-equivalents, ahead of Anthropic-Amazon New Carlisle at 686,000.
- DayOne Nusajaya in Johor Bahru, Malaysia, rounds out the top five at 584,000 H100-equivalents, and sits outside the US-only chart below.
- Anthropic-Amazon New Carlisle, Microsoft Fairwater Atlanta and Meta Prometheus have each claimed the top spot at different times.
View the data
Key finding: Since the launch of SpaceXAI’s Colossus 1 in August 2024, the record for the largest AI data center by computing capacity has doubled every seven months, per Epoch AI. Epoch AI expects a reversion to that trend in late 2027 or early 2028, when QTS Cedar Rapids and Meta Hyperion are projected to be completed.
Recent Developments
- Oct. 12, 2026: Epoch AI’s AI data center data, updated Oct. 12, 2026, covers 94 sites with 14.1 GW of IT power and 44% coverage.
- Sept. 10, 2026: Oracle reported Q1 FY27 results with the delivery of 850 MW of additional data center capacity, and said customer demand for AI Cloud Training and Inferencing Services continues to grow faster than supply.
- July 28, 2026: Meta announced a venture with BlackRock for its El Paso, Texas campus, which will have 1 gigawatt of compute capacity and is expected to begin bringing capacity online in 2028.
- Quarter ended July 26, 2026: NVIDIA said its Vera Rubin platform is ramping into full production, with racks running at CoreWeave, Google Cloud, Microsoft Azure, Oracle Cloud Infrastructure and Nebius.
- July 22, 2026: Georgia Power said OpenAI is expected to need approximately 3,200 MW of power for its new Effingham County facility, and that OpenAI has agreed to provide up to 1,000 MW of flexible demand response.
How Much AI Data Center Capacity Is Being Built
- Total facility power is 20 to 50% higher than IT power due to cooling and other overhead, taking the 94 covered sites to 18.3 GW of capacity.
- OpenAI’s announcements cover at least 26 GW: at least 10 GW of NVIDIA systems, 6 GW of AMD GPUs and 10 GW of OpenAI-designed accelerators with Broadcom.
- Stargate’s seven sites add up to over 9 GW of planned capacity, which Epoch AI compares to the peak power demand of New York City.
- That planned capacity would power the equivalent of 20 million NVIDIA H100 GPUs, the total amount of AI compute in the world by the end of 2025.
- Announced gigawatts are letters of intent and supply agreements, not built capacity, so they cannot be added to Epoch AI’s measured total.
| Measure | Power (GW) |
|---|---|
| Total facility capacity, 94 covered sites | 18.3 |
| IT power capacity, 94 covered sites | 14.1 |
| New York City peak demand | 11 |
Source: Epoch AI (October 2026)
Why it matters: OpenAI’s agreements with NVIDIA, AMD and Broadcom cover at least 26 GW, set beside the 14.1 GW of IT power and 18.3 GW of total facility power Epoch AI counts across its 94 covered sites. OpenAI’s announcements do not say whether their gigawatts are IT or facility power, so the figures sit side by side rather than as a ratio. Most of that signed capacity would land in campuses that are not yet built, so it describes intent rather than hardware in service.
How much power does an AI data center use?
Individual AI data centers range from under 50 MW, enough to power a small city like Albany, NY, to over 1,000 MW, enough to power a mid-sized city like San Diego, CA, per Epoch AI. The IEA says a typical AI-focused data center consumes as much electricity as 100,000 households, while the largest under construction today will consume 20 times as much. The gap between installed capacity and average draw is why data center electricity use is measured separately from installed megawatts.
Where AI Data Centers Are Being Built
- The United States has the most large-scale AI data centers, led by Texas with 14 sites covered.
- Ohio and Virginia follow with 7 sites covered each.
- Many new sites are clustered near major power infrastructure and fiber networks in the American Midwest and South.
- International facilities include DayOne Nusajaya in Johor Bahru, Malaysia, and DayOne Kempas in Kempas, Malaysia.
- Stargate’s most advanced site is in Abilene, Texas, and two more of its sites are in Texas, which places OpenAI’s flagship program inside the Texas data center market.
View the data
The counts are sites in Epoch AI’s coverage, not every data center in each state.
OpenAI Stargate Sites and Capacity
- The Stargate Project intends to invest $500 billion over the next four years building new AI infrastructure for OpenAI in the United States.
- OpenAI said the project would begin deploying $100 billion immediately.
- The initial equity funders in Stargate are SoftBank, OpenAI, Oracle and MGX.
- OpenAI said its five new sites, the Abilene flagship and its CoreWeave projects, brought Stargate to nearly 7 gigawatts of planned capacity and over $400 billion in investment over the next three years.
- OpenAI and Oracle agreed to develop up to 4.5 gigawatts of additional Stargate capacity, a partnership that exceeds $300 billion over the next five years.
- OpenAI, Oracle and SoftBank reviewed over 300 proposals from more than 30 states.
- At least three of the seven sites will use on-site natural gas plants, and at least six will use closed-loop liquid cooling systems.
| Site | Current capacity (GW) | Projected capacity (GW) | Construction began | Projected completion | Power sources |
|---|---|---|---|---|---|
| Abilene, Texas | 0.3 | 1.2 | Q2 2024 | Q4 2026 | On-site gas, Grid |
| Shackelford County, Texas | 0 | 2.0 | Q3 2025 | Q4 2028 | On-site gas |
| Doรฑa Ana County, New Mexico | 0 | 2.2 | Q4 2025 | Q4 2028 | On-site gas |
| Milam County, Texas | 0 | 1.2 | Q3 2025 | Q4 2028 | On-site (unknown type) |
| Port Washington, Wisconsin | 0 | 1.3 | Q1 2026 | Q4 2028 | Grid |
| Saline Township, Michigan | 0 | 1.4 | Q4 2025 | Q4 2028 | Grid |
| Lordstown, Ohio | 0 | <0.3 | Q4 2025 | Unknown | Grid |
Source: Epoch AI (April 2026), total facility power
Where are the Stargate data centers being built?
Stargate has seven locations across the US: Abilene, Texas, two more sites in Texas, and facilities in New Mexico, Wisconsin, Michigan, and Ohio. Epoch AI lists them as Abilene, Shackelford County and Milam County in Texas, Doรฑa Ana County in New Mexico, Port Washington in Wisconsin, Saline Township in Michigan and Lordstown in Ohio.
Stargate Abilene Build Progress
- Epoch AI estimates Abilene’s current capacity at 0.3 GW and 250,000 H100-equivalents, with 1.2 GW projected by Q4 2026, as of its April 2026 Stargate report.
- Built by Crusoe, Abilene has an estimated four of its eight buildings operational, housing NVIDIA Blackwell chips.
- Epoch AI’s site page puts Abilene at 421 MW of IT power and 509,000 H100-equivalents now, and 843 MW and 1,019,000 H100-equivalents projected.
- OpenAI had planned to expand Abilene to 2.1 GW but reversed course, and Microsoft has since partnered with Crusoe for the adjacent 900 MW site.
- Epoch AI projects 4.6 million H100-equivalents for Doรฑa Ana County, New Mexico, on 2.2 GW of projected capacity.
- Vantage is constructing a 1,200-acre campus with 10 buildings for the Shackelford County site, powered by an onsite natural gas microgrid.
View the data
Worth noting: All stated Stargate power capacities refer to total facility power, and the sites have not been reported consistently as total facility power or IT power. Vantage, for example, reports Shackelford County as 1.4 GW of IT power, against 2.0 GW of projected capacity in Epoch AI’s site table. The 0.3 GW and 421 MW Abilene readings measure different things on different dates.
OpenAI Compute Deals by Gigawatt
- NVIDIA and OpenAI signed a letter of intent to deploy at least 10 gigawatts of NVIDIA systems, and NVIDIA intends to invest up to $100 billion in OpenAI progressively as each gigawatt is deployed.
- The first gigawatt of NVIDIA systems will be deployed in the second half of 2026 on NVIDIA’s Vera Rubin platform.
- AMD has issued OpenAI a warrant for up to 160 million shares of AMD common stock, structured to vest as specific milestones are achieved.
- OpenAI will design the Broadcom accelerators and systems, which will be developed and deployed in partnership with Broadcom.
- Under the 25-year agreement, Georgia Power will have the ability to reduce energy delivered to the OpenAI facility during certain times to support grid stability. That load joins Microsoft Fairwater Atlanta among Georgia data center projects.
| Partner | Capacity | Agreement | Timing |
|---|---|---|---|
| NVIDIA | At least 10 GW of NVIDIA systems | Letter of intent | First gigawatt in second half of 2026 |
| Broadcom | 10 GW of custom AI accelerators | Term sheet | Racks from second half of 2026 to end of 2029 |
| AMD | 6 GW of AMD GPUs | Multi-year, multi-generation agreement | First 1 GW of MI450 GPUs in second half of 2026 |
| Oracle | Up to 4.5 GW of Stargate capacity | Agreement to develop | Over the next five years |
| Georgia Power | Approximately 3,200 MW of power need, with up to 1,000 MW of flexible demand response | 25-year agreement | Announced July 2026 |
Source: OpenAI (2025); Georgia Power (July 2026)
Meta Prometheus and Hyperion AI Data Centers
- Meta Prometheus has 471 MW of IT power, and Epoch AI puts its compute at 536,000 H100-equivalents in New Albany, OH.
- Meta Hyperion is projected to be completed in late 2027 or early 2028, per Epoch AI.
- Meta says its Richland Parish Data Center will deliver over two gigawatts of compute capacity to train future open-source large language models.
- Over 2,300 workers are already onsite at Meta’s El Paso campus, which the venture expects to begin bringing online in 2028.
- Funds managed by BlackRock will own an 80% interest in the El Paso venture, while Meta will retain the remaining 20%.
- Meta anticipates 2026 capital expenditures, including principal payments on finance leases, in the range of $130 billion to $145 billion, one of the outlays behind hyperscaler capex and cash flow.
| Measure | Richland Parish, Louisiana | El Paso, Texas |
|---|---|---|
| Compute capacity | Over 2 gigawatts | 1 gigawatt |
| Meta investment | Over $50 billion | Over $10 billion |
| Construction workers at peak | Over 7,500 | More than 4,000 |
| Operational jobs once complete | 1,000 | 300 |
Source: Meta (July and October 2026)
Both campuses in the table are company plans; the Epoch AI figures for Prometheus and Hyperion in this section are modeled.
Microsoft Fairwater AI Data Centers
- Epoch AI estimates Microsoft Fairwater Atlanta hosts 769,000 H100-equivalents of AI compute, supported by 636 MW of IT power.
- Microsoft says its Fairwater AI data center in Wisconsin covers 315 acres, with three buildings and a combined 1.2 million square feet under roofs.
- Microsoft says the site works as one AI supercomputer, using a single flat network to interconnect hundreds of thousands of the latest NVIDIA GPUs.
- Microsoft has multiple identical Fairwater data centers under construction in other US locations, and each rack packs 72 NVIDIA Blackwell GPUs.
- Microsoft says these AI data centers represent tens of billions of dollars of investment and connect with a Microsoft Cloud of over 400 data centers in 70 regions.
| Construction input at Fairwater, Wisconsin | Quantity |
|---|---|
| Deep foundation piles | 46.6 miles |
| Structural steel | 26.5 million pounds |
| Medium-voltage underground cable | 120 miles |
| Mechanical piping | 72.6 miles |
Source: Microsoft (September 2025)
SpaceXAI Colossus GPU Count
- SpaceXAI says Colossus was built in 122 days, then doubled in 92 days to 200,000 GPUs.
- The company says it was told the build would take 24 months and accomplished its goal in four months.
- Meta, SpaceXAI and Microsoft primarily use NVIDIA GPUs, while Google uses custom TPUs and Amazon deploys Trainium.
- SpaceXAI’s build times and GPU count describe the original Colossus, launched in August 2024, while Epoch AI’s modeled estimates describe Colossus 2, so the rows below cover two different sites.
| Measure | Figure | Stated by |
|---|---|---|
| Original Colossus, initial build time | 122 days | SpaceXAI |
| Original Colossus, time to double the cluster | 92 days | SpaceXAI |
| Original Colossus, GPUs after doubling | 200,000 | SpaceXAI |
| SpaceXAI GPU roadmap | 1 million | SpaceXAI |
| Colossus 2 IT power | 946 MW | Epoch AI estimate |
| Colossus 2 compute | 1,112,000 H100-equivalents | Epoch AI estimate |
Source: SpaceXAI; Epoch AI (October 2026)
Amazon Project Rainier and Anthropic Compute
- Amazon says Project Rainier provides more than five times the compute power Anthropic used to train its previous AI models.
- AWS deployed Project Rainier less than one year after it was first announced.
- AWS says Project Rainier’s Trainium2 infrastructure is 70% larger than any other AI computing platform in AWS history.
- An UltraServer combines four Trainium2 servers, each with 16 Trainium2 chips, and St. Joseph County, Indiana, is one of the Project Rainier sites.
- Anthropic says its compute strategy uses three chip platforms: Google’s TPUs, Amazon’s Trainium and NVIDIA’s GPUs.
| Program | Chips or capacity | Stated by |
|---|---|---|
| Project Rainier | Nearly half a million Trainium2 chips | Amazon |
| Claude on Trainium2 | More than 1 million Trainium2 chips | Amazon |
| Google Cloud TPU expansion | Up to one million TPUs, expected to bring well over a gigawatt online in 2026 | Anthropic |
| Fluidstack data centers in Texas and New York | $50 billion investment | Anthropic |
| Anthropic-Amazon New Carlisle | 910 MW of IT power | Epoch AI estimate |
Source: Amazon (2025); Anthropic (2025); Epoch AI (October 2026)
Chip counts and gigawatts in this table are not interchangeable: Trainium2, TPU, and H100-equivalent figures each measure a different unit.
GPU Counts in AI Data Centers
- Epoch AI’s AI Chip Sales database estimates about 20 million H100-equivalents worth of AI chips sold by Q4 2025.
- Epoch AI estimates global computing capacity has grown by 3.3x per year since 2022 (90% CI: 2.7x to 4.1x), equivalent to a doubling time of 7 months.
- NVIDIA AI chips account for over 60% of total compute, with Google and Amazon making up much of the remainder, per Epoch AI.
- Major AI data centers deploy NVIDIA H100, H200 and B200 GPUs, Google TPU v5 and v6 chips, and AWS Trainium2 accelerators.
- NVIDIA reported total company revenue of $96,221 million for Q2 FY27, up 106% from a year ago.
- NVIDIA’s Data Center segment brought in $89.0 billion of that total, up 117% from a year ago.
- H100-equivalents measure compute, not chip units, so they cannot be compared directly with chip counts such as Project Rainier’s.
View the data
How many GPUs are in an AI data center?
Epoch AI estimates Microsoft Fairwater Atlanta uses 304,300 NVIDIA B200 chips, SpaceXAI says Colossus doubled to 200,000 GPUs, and Crusoe disclosed 50,000 Blackwell GPUs per building at Abilene. Counts differ widely because sites differ in size and owners disclose different units. The models trained on these chips feed the enterprise uptake measured in machine learning adoption figures.
AI Data Center Construction Costs
- Epoch AI puts Stargate Abilene’s projected cost at $31.9 billion.
- Abilene’s projected cost is about 2.0 times its current cost estimate, as its IT power rises from 421 MW to a projected 843 MW.
- Meta and BlackRock’s El Paso venture carries approximately $14 billion in total development costs, and part of BlackRock’s investment will be funded with $12.5 billion in debt financing.
- Anthropic’s $50 billion program will create approximately 800 permanent jobs and 2,400 construction jobs, with sites coming online throughout 2026.
- Those per-campus figures sit inside total data center construction spending, which covers the wider industry.
View the data
By the numbers: The IEA says global investment in data centers has nearly doubled since 2022 and amounted to half a trillion dollars in 2024. Epoch AI estimates single campuses at $24.1 billion for Microsoft Fairwater Atlanta and $31.9 billion for Stargate Abilene at full build-out. The IEA total is 2024 spending, while Epoch AI’s campus figures are capital cost estimates, so the two are not compared directly.
How much does an AI data center cost to build?
Epoch AI estimates Microsoft Fairwater Atlanta, with 636 MW of IT power, at a capital cost of $24.1 billion. Meta’s El Paso campus, with 1 gigawatt of compute capacity, carries approximately $14 billion in total development costs. Industry-wide totals are in the data center industry figures.
AI Cloud Capacity at Oracle and CoreWeave
- Oracle booked more than $30 billion of additional AI cloud contracts in Q1, increasing its RPO to $664 billion.
- Cloud revenues increased 62% to $11.6 billion, driven by 121% growth in Cloud Infrastructure.
- Oracle’s capital expenditures were $28,499 million in Q1 FY27, up from $8,502 million in Q1 FY26, according to its quarterly results filing.
- CoreWeave expanded active power by nearly 500 MW to reach 1.5 GW, and grew total contracted power to approximately 3.7 GW.
- CoreWeave’s revenue backlog was approximately $104 billion as of June 30, 2026, not including more than $25 billion of net new customer commitments added in early Q3.
- Oracle and CoreWeave sell this capacity as cloud services; the market tracked in cloud computing figures.
View the data
Conclusion
The 94 AI data centers Epoch AI covers hold 14.1 GW of IT power, while OpenAI’s chip agreements alone cover at least 26 GW. For buyers, analysts and reporters, the useful habit is to keep three measures apart: signed gigawatts, Epoch AI’s modeled estimates and company chip counts each describe a different stage of the same build-out.
Stargate’s seven sites add up to over 9 GW of planned capacity, while Abilene operates at an estimated 0.3 GW in Epoch AI’s April 2026 report. Epoch AI expects the single-site compute record to resume its trend when QTS Cedar Rapids and Meta Hyperion are completed, and until then the gap between announced and operating capacity is the figure to watch.