Data Center Construction Statistics 2026: Costs, Pipeline and Delays

Published on: October 28, 2026
Brad Nickel
Senior Content Writer • 29 Articles
Brad Nickel founded Tricity Local News in March 2025. He is a technology writer and industry strategist specializing in artificial intellige...
LATEST POSTS:
Cloud Market Share Statistics 2026: Largest Cloud Providers Ranked
Largest Data Centers in the US Statistics 2026: Sites and Capacity
How Many Jobs Do Data Centers Create? Statistics 2026: Jobs per Site
Alice Meckler
Senior Content Editor • 10 Articles
Alice Meckler is a renowned business strategist and labor market analyst with deep expertise in employment dynamics, workforce optimization,...
LATEST POSTS:
DevOps Statistics 2026: DORA Metrics, AI Adoption and Developer Pay
Behind the Trial: Shocking Four-Day Workweek Statistics You Need to See
Mind-Blowing Nursing Workforce Statistics That Reveal the Future of Healthcare
Data Center Construction Statistics 2026: Costs, Pipeline and Delays
Share on LinkedIn ChatGPT Perplexity Share on X Share on Facebook

US private data center construction ran at a seasonally adjusted annual rate of $84,950 million in August 2026, up 73.2% from $49,052 million in August 2025, according to the US Census Bureau. For calendar 2025, the Census Bureau put the value of private data center construction at $49,737 million, against $12,583 million in 2022.

Those totals count the building and leave out the computers inside it. JLL is forecasting the average global cost will increase 6% to $11.3 million per MW in 2026, and CBRE counted 7,481 megawatts (MW) under construction in H1 2026 across eight primary North American markets. JLL also says the average wait time for a grid connection in primary data center markets exceeds four years. Each figure below carries its source and date, alongside the wider data center statistics.

Key Takeaways

  • Data center construction was about 11.0% of the $773,010 million annual rate for all private nonresidential construction in August 2026, per Census Bureau figures.
  • The 2025 data center total of $49,737 million was about 3.95 times the 2022 level in the Census annual series.
  • The Census Bureau excludes racks or servers in data centers from construction, while JLL says tech fit-out can cost as much as $25 million per MW for AI infrastructure.
  • JLL’s construction cost figures only include the cost to construct the shell and core, and the average global data center construction cost increased from $7.7 million to $10.7 million per MW between 2020 and 2025.
  • CBRE reports new construction rose 24.8% across the eight primary North American data center markets in the first half of 2026.
  • JLL’s 66 GW under construction in North America is about 8.8 times CBRE’s 7,481 MW, because the two firms count different markets.

Editor’s Choice

  • Capacity under construction, North America: JLL reports 66 GW under construction, 95% of which is pre-committed.
  • Preleased share of CBRE’s pipeline: more than 80% of all capacity under construction is already preleased, up from 74.3% a year ago.
  • Atlanta under construction: CBRE counts nearly 2,900 MW under construction, overtaking Northern Virginia.
  • Construction cost inflation, 2025: Turner & Townsend finds cost inflation for traditional data centers worldwide averaging 5.5% in 2025.
  • AI construction cost premium: Turner & Townsend identifies a 7-10% construction cost premium between traditional and AI data centers in the US.
  • Permanent debt originations: JLL expects construction activity to drive more than $700 billion in permanent debt originations over the next 30 months.

Data Center Construction Spending by Month

  • The Census Bureau put private data center construction at $84,950 million in August 2026 (preliminary), up 7.5% from July 2026 at a seasonally adjusted annual rate.
  • That rate equals $84.95 billion a year.
  • Data center construction in August ran about 37.3% above the April 2026 rate.
  • Total US construction spending was a seasonally adjusted annual rate of $2,203.1 billion in August 2026, 1.7% below the August 2025 estimate.
  • Spending on private construction was at a seasonally adjusted annual rate of $1,655.3 billion in the same release.
  • An annual rate is one month’s spending expressed as a yearly pace, so it is not money spent in that month.
MonthPrivate data center construction, annual rate ($ millions)
Aug 202549,052
Apr 202661,859
May 202665,688
Jun 2026 (revised)72,695
Jul 2026 (revised)79,007
Aug 2026 (preliminary)84,950

Source: US Census Bureau, Value of Private Construction Put in Place (October 2026)

About This Data

  • 22 sources on 10 pages: 6 from the US Census Bureau’s construction spending tables, release and definitions, and 16 from CBRE, JLL, Turner & Townsend, and the Uptime Institute.
  • Publication window: Turner & Townsend’s 2025-2026 cost index release, JLL’s 2026 Global Data Center Outlook, and July 2026 to October 2026 for the rest.
  • Selection: government statistics, named real estate and cost consultancies, and an industry survey body; paid market-research report sellers excluded.
  • Figures are reviewed on a rolling basis and updated when sources publish new editions.
Envelope holding a monthly statistics report with a rising chart
Get the month's tech statistics in one email

You get one briefing a month with the statistics we published or refreshed, and the source for each figure.

One email a month. Unsubscribe anytime.

How much is being spent on data center construction?

The Census Bureau estimates private data center construction at a seasonally adjusted annual rate of $84,950 million in August 2026, or $84.95 billion a year. The US Census Bureau announced the August 2026 construction statistics on October 1, 2026. The rate is a yearly pace, so it is a measure of momentum. One strong month can mislead; the calendar-year totals show the climb.

Annual Data Center Construction Spending, 2022 to 2025

  • The Census Bureau put private data center construction at $49,737 million in 2025, up from $34,797 million in 2024, an increase of about 42.9%.
  • The 2025 total was about 3.95 times the $12,583 million recorded for 2022.
  • Data center construction’s August 2026 annual rate was about 1.71 times the $49,737 million calendar-year total for 2025.
  • Prior to 2014, expenditures for data centers were included as part of general office, so the series has no separate history before then.
PRIVATE DATA CENTER · Source: US Census Bureau, Annual Value of Private Construction Put in Place 2022 to 2025 (2026) PRIVATE DATA CENTER US Census Bureau · 2022 to 2025 Private Data Center Construction Spending by Year ($ millions) 50K 37.5K 25K 12.5K 0 12,583 2022 19,995 2023 34,797 2024 49,737 2025 SOURCE US Census Bureau, Annual Value of Private Construction Put in Place 2022 to 2025 (2026)
View the data
Year$ millions
202212,583
202319,995
202434,797
202549,737

Those totals also say something about every other kind of building.

Recent Developments

  • October 1, 2026: The Census Bureau reported construction spending during August 2026 at a seasonally adjusted annual rate of $2,203.1 billion, 0.9% above the revised July estimate.
  • September 8, 2026: CBRE reported that Northern Virginia remains North America’s largest data center market, adding more than 1 gigawatt of inventory as vacancy falls to 0.2%.
  • August 11, 2026: JLL reported vacancy sustained at 1% for the third consecutive year despite unprecedented construction activity in North America.
  • July 28, 2026: The Uptime Institute released the findings of its 16th Annual Global Data Center Survey, which highlights escalating concerns over capacity forecasting, power availability, and supply chain disruptions.
  • First half of 2026: CBRE found that across North America’s primary markets, net absorption increased by nearly 12% to 1,456 MW, while vacancy held steady at 1.4%.

Data Center vs Office and Nonresidential Construction

  • Data center construction at $84,950 million ran at about 1.85 times general office construction of $45,809 million in August 2026.
  • Private nonresidential construction was $773,010 million, down 1.0% from August 2025, at a seasonally adjusted annual rate.
  • Data center construction was about 11.0% of that nonresidential total in August 2026.
  • The office category ran at $134,119 million, against $103,300 million in August 2025, a rise of about 29.8%, while general office fell about 9.7% from $50,724 million.
  • For calendar 2025, data centers were about 6.3% of the $783,741 million in private nonresidential construction.
  • General office construction fell from $67,662 million in 2022 to $51,028 million in 2025.
  • The Census Bureau files data centers under the office category, so the office total rises with them.
ANNUAL RATE, AUGUST 2026 · Source: US Census Bureau, Value of Private Construction Put in Place (October 2026) ANNUAL RATE, AUGUST 2026 US Census Bureau · 2026 Private Construction Annual Rate by Type ($ millions) Data center 84,950 General office 45,809 Lodging 23,328 0 20K 40K 60K 80K 100K SOURCE US Census Bureau, Value of Private Construction Put in Place (October 2026)
View the data
Construction type$ millions
Data center84,950
General office45,809
Lodging23,328

By the numbers: The Census Bureau’s August 2026 table puts data center construction at $84,950 million and general office at $45,809 million, with private nonresidential construction down 1.0% from a year earlier. One building type is now carrying the office category while total nonresidential building slips.

That figure is large, and it still leaves out the equipment inside.

What Census Data Center Construction Spending Counts

  • The Census Bureau’s data center category includes buildings that contain the hardware needed for storing, processing, and transmitting digital information.
  • Special-purpose equipment, such as racks or servers in data centers, is excluded from construction in the Census definitions.
  • Maintenance and repairs to existing structures or service facilities are also excluded from construction.
  • JLL notes that tenants are typically responsible for the tech fit-out, which can cost as much as $25 million per MW for AI infrastructure.
MeasureWhat it coversWhat it leaves outSource
Value of data center construction put in placeBuildings that contain the hardware for storing, processing, and transmitting digital informationRacks or servers; maintenance and repairsUS Census Bureau
Average global construction cost per MWShell and coreTenant tech fit-outJLL
Tech fit-out cost for AI infrastructureas much as $25 million per MWShell and coreJLL

Source: US Census Bureau construction spending definitions (2026); JLL 2026 Global Data Center Outlook

Does Census data center spending include servers?

No. The Census definitions list racks or servers in data centers among special-purpose equipment excluded from construction. The data center category includes buildings that contain the hardware needed for storing, processing, and transmitting digital information, so the series measures the building that holds the servers, and the servers themselves sit outside it. Cost firms price that shell per megawatt.

Data Center Construction Cost per MW

  • JLL reports that data center construction costs have been increasing at a 7% CAGR between 2020 and 2025, in global averages.
  • JLL is forecasting the average global cost will increase 6% to $11.3 million per MW for 2026.
  • JLL’s $11.3 million global average shell-and-core forecast plus the top of its AI fit-out range, which can cost as much as $25 million per MW, comes to about $36.3 million per MW.
  • JLL says speed to power is the primary criterion driving site selection, followed by community support, latency, and proximity to customers.
  • JLL’s averages are global, so a US project can sit above or below them.
AVERAGE GLOBAL CONSTRUCTION COST · Source: JLL, 2026 Global Data Center Outlook AVERAGE GLOBAL CONSTRUCTION COST JLL · 2026 Global Construction Cost per MW ($ millions) 12 9 6 3 0 7.7 2020 10.7 2025 11.3 2026 (forecast) SOURCE JLL, 2026 Global Data Center Outlook
View the data
Year$ millions
20207.7
202510.7
2026 (forecast)11.3

Worth noting: JLL’s $11.3 million per MW is a global average forecast, and JLL notes that its construction cost figures only include the cost to construct the shell and core. Fit-out sits on top of it, and the Census Bureau leaves servers out of its spending series, so neither number describes the full cost of a finished, equipped data center.

How much does it cost to build a data center per MW?

JLL is forecasting the average global cost will increase 6% to $11.3 million per MW in 2026. The figures only include the cost to construct the shell and core, and tech fit-out can cost as much as $25 million per MW for AI infrastructure, so an AI build can cost far more per MW. Per-watt indexes show how far costs vary by market.

Data Center Construction Cost per Watt by Market

  • Turner & Townsend’s analysis of the current cost per watt to build data centers in 52 markets worldwide ranks Tokyo first.
  • The same analysis shows cost inflation for traditional data centers worldwide averaging 5.5% in 2025.
  • Tokyo had the highest construction cost per watt at $15.2, followed by Singapore at $14.5.
  • Silicon Valley ranked fifth at $13.3 per watt and New Jersey sixth at $12.9, the two US markets in the top 10.
  • Stockholm and Helsinki matched Auckland at $12.3 per watt, filling places 8 to 10.
  • Turner & Townsend identifies a 7-10% construction cost premium between traditional and AI data centers in the US, comparing projects of similar IT capacity.
  • Turner & Townsend’s per-watt index and JLL’s per-MW average use different methods and market sets, so the two series are read side by side and never merged.
COST PER WATT · Source: Turner & Townsend, Data Centre Construction Cost Index 2025-2026 COST PER WATT Turner & Townsend · 2025 to 2026 Construction Cost per Watt, Top 8 Markets ($) Tokyo $15.2 Singapore $14.5 Zurich $14.2 Osaka $14.1 Silicon Valley $13.3 New Jersey $12.9 Oslo $12.4 Auckland $12.3 0 4 8 12 16 SOURCE Turner & Townsend, Data Centre Construction Cost Index 2025-2026
View the data
MarketCost per watt ($)
Tokyo15.2
Singapore14.5
Zurich14.2
Osaka14.1
Silicon Valley13.3
New Jersey12.9
Oslo12.4
Auckland12.3

Cost is one constraint; capacity on the ground is the other.

Data Center Capacity Under Construction in North America

  • CBRE reports that the 7,481 megawatts (MW) under construction in H1 2026 surpassed the previous high reached in 2024.
  • More than 80% of all capacity under construction is already preleased, up from 74.3% a year ago, per CBRE.
  • Less than 1,500 MW is available for pre-leasing across North America’s primary markets, roughly six months of supply at the current pace of demand, per CBRE.
  • CBRE says Atlanta emerged as North America’s most active construction market for the first time, with nearly 2,900 MW under construction. Those projects are tracked in the Georgia data center pipeline.
  • JLL finds frontier markets now account for 77% of all capacity under development.
  • JLL also counts 28 GW of owner-occupied capacity currently under construction by hyperscalers.
  • JLL’s 66 GW under construction in North America is about 8.8 times CBRE’s 7,481 MW, because CBRE counts only eight primary markets.
MeasureScopeFigureSource
Capacity under constructionEight primary North American markets, H1 20267,481 MWCBRE
Capacity under constructionAtlanta, H1 2026nearly 2,900 MWCBRE
Share of capacity under construction preleasedEight primary marketsMore than 80%CBRE
Capacity under constructionNorth America66 GWJLL
Share of capacity under construction pre-committedNorth America95%JLL
Existing and under-construction capacityTexas26 GWJLL
Existing and under-construction capacityVirginia13 GWJLL

Source: CBRE, North American Data Center Trends H1 2026 (September 2026); JLL, North America Data Center Report Midyear 2026 (August 2026)

How many megawatts of data centers are under construction?

CBRE counts 7,481 megawatts (MW) under construction in H1 2026 across eight primary markets, and JLL counts 66 GW under construction in North America. JLL puts Texas at 26 GW of existing and under-construction capacity, followed by Virginia at 13 GW; see the Texas data center figures and the Virginia data center market. Most of that capacity already has a tenant.

Who Data Centers Are Being Built For

  • JLL says hyperscalers remain the dominant force, accounting for 59% of 2026 data center tenant demand.
  • CBRE reports average asking rents rose for every major deployment size in the first six months of the year, led by an 8.3% increase for users seeking between 3 MW and 10 MW of capacity.
  • JLL’s shares do not sum to 100, so the chart shows them as bars. The spending behind the largest tenants sits in the hyperscale data center statistics.
SHARE OF 2026 TENANT DEMAND · Source: JLL, North America Data Center Report Midyear 2026 (August 2026) SHARE OF 2026 TENANT DEMAND JLL · 2026 Share of Data Center Tenant Demand by Tenant Type, 2026 (%) Hyperscalers 59% Neoclouds 11% Pure-play AI companies 7% 0 12 24 36 48 60 SOURCE JLL, North America Data Center Report Midyear 2026 (August 2026)
View the data
Tenant typeShare of 2026 tenant demand (%)
Hyperscalers59
Neoclouds11
Pure-play AI companies7

Signed tenants do not make power arrive sooner.

Data Center Construction Delays and Power Constraints

  • JLL says data center operators are expected to increase behind-the-meter power arrangements and explore colocated battery storage as the average wait time for a grid connection in primary data center markets exceeds four years.
  • In Turner & Townsend’s survey of industry leaders, 48% said power availability is the most prominent obstacle to delivering projects on schedule.
  • CBRE says power-related project delays briefly softened activity at the end of last year, and power constraints are extending completion timelines.
  • The Uptime Institute reports that more than half of all respondents in 2026 report difficulties finding qualified candidates for open positions, based on responses from more than 800 data center owners and operators.
  • JLL finds that while 79% of Americans support US leadership in artificial intelligence, only 14% support data center development in their community.
  • The demand side of that power queue is covered in the data center electricity consumption figures.
ConstraintFigureSource
Average wait for a grid connection, primary marketsexceeds four yearsJLL
Power availability named the top obstacle to on-schedule delivery48% of respondentsTurner & Townsend
Local supply chains not well prepared for advanced cooling83% of respondentsTurner & Townsend
Difficulty finding qualified candidatesMore than half of respondentsUptime Institute
Support for data center development in their community14% of AmericansJLL

Source: JLL 2026 Global Data Center Outlook and Midyear 2026 report; Turner & Townsend Data Centre Construction Cost Index 2025-2026; Uptime Institute 2026 Global Data Center Survey

Key finding: Turner & Townsend’s survey shows it is power and supply chain capacity to deliver these AI data centers, rather than cost, which is raising concern within the sector. With JLL’s grid queue above four years, a project’s start date says less about its finish date than its place in the utility’s connection line.

Why are data center construction projects delayed?

Power is the most-cited reason. JLL says the average wait time for a grid connection in primary data center markets exceeds four years, and 48% of Turner & Townsend’s respondents said power availability is the most prominent obstacle to delivering projects on schedule. CBRE adds that power constraints are extending completion timelines. Lenders are pricing the build-out as if those waits will clear.

Data Center Construction Financing

  • Commercial mortgage-backed securities and asset-backed security data center volume combined for $17 billion in the first half of 2026, a 29% increase from the previous year, per JLL.
  • Non-credit tenant deals are evaluated ad hoc with spreads approximately 200 to 300 basis points wider than investment-grade hyperscaler construction loans.
  • The global data center sector is estimated to grow at a 14% CAGR over the next five years, according to JLL.
MeasureFigurePeriodSource
Permanent debt originations driven by construction (forecast)more than $700 billionNext 30 monthsJLL
CMBS and ABS data center volume$17 billionFirst half of 2026JLL
Investment required for 100 GW of new supply (estimate)$3 trillionThrough 2030JLL

Source: JLL, North America Data Center Report Midyear 2026 (August 2026); JLL 2026 Global Data Center Outlook

Is data center construction slowing down?

Not on the latest data. The Census Bureau put the August 2026 annual rate up 7.5% from July and 73.2% from a year earlier, and CBRE reports new construction rose 24.8% across the eight primary North American data center markets in the first half of 2026. Grid waits slow individual projects more than the overall pace.

Conclusion

US private data center construction ran at $84,950 million at a seasonally adjusted annual rate in August 2026, up 73.2% from a year earlier, per the Census Bureau. That number counts the building only, and JLL’s per-MW cost and CBRE’s and JLL’s capacity counts each measure a different slice, so they are read side by side and never added up.

JLL expects the global data center sector to grow at a 14% CAGR over the next five years. Whether that capacity arrives on time depends on the grid connection queue.

This article has been reviewed and fact-checked by Alice Meckler. Tricity Local News follows strict Publishing Principles and a documented Fact-Check Policy to ensure accuracy, transparency, and editorial independence across all content. Our statistics are verified using a documented Research Process.

See more Tricity Local News stories in Google’s Top Stories. Add as a preferred
source on Google

Share these figures

Researched and verified by our team, so every figure holds up when you pass it on.

  • Share on X
  • Share on LinkedIn
  • Share on Facebook
  • Share on WhatsApp
  • Share by email
Summarize withChatGPT (opens in a new tab)Perplexity (opens in a new tab)

Cite this article

Citation format

Nickel, B. (2026, October 28). Data Center Construction Statistics 2026: Costs, Pipeline and Delays. Tricity Local News. https://tricitylocalnews.com/data-center-construction-statistics/Nickel, Brad. “Data Center Construction Statistics 2026: Costs, Pipeline and Delays.” Tricity Local News, 28 Oct. 2026, https://tricitylocalnews.com/data-center-construction-statistics/Nickel, Brad. “Data Center Construction Statistics 2026: Costs, Pipeline and Delays.” Tricity Local News, October 28, 2026. https://tricitylocalnews.com/data-center-construction-statistics/Data Center Construction Statistics 2026: Costs, Pipeline and Delays, Tricity Local Newshttps://tricitylocalnews.com/data-center-construction-statistics/

APA 7th edition, the style most research and reports use.MLA 9th edition.Chicago notes and bibliography.Pastes as a clickable link in WordPress, Google Docs and most email editors.

References

  • Value of Private Construction Put in Place, Seasonally Adjusted Annual Rate (August 2026)
  • Annual Value of Private Construction Put in Place 2022 - 2025
  • Monthly Construction Spending, August 2026 (CB26-158)
  • Construction Spending: Definitions
  • North American Data Center Demand Continues to Outpace Supply Despite Record Construction Activity
  • Data center demand exceeds expectations as H1 2026 absorption hits record 25 GW
  • 2026 Global Data Center Outlook
  • AI data center rush raises alarm over construction supply chain (Data Centre Construction Cost Index 2025-2026)
  • Uptime Institute 16th Annual Global Data Center Survey 2026

Brad Nickel

Senior Content Writer


Brad Nickel founded Tricity Local News in March 2025. He is a technology writer and industry strategist specializing in artificial intelligence, machine learning, and cloud computing. He holds a Master of Science in Computer Science from Yale University, where he focused on advanced computational models. At Tricity Local News he writes the Cloud and Hosting coverage, reviews the AI and Enterprise IT pages, and breaks down complex AI developments, emerging tech trends, and cloud innovations for a growing digital audience.

Related Posts

Data Centers in Ohio 2026: Statistics on Power and Load
Cloud

Data Centers in Ohio Statistics 2026: Power, Load and Projects

Largest Data Center Companies 2026: Capacity, Sites and Revenue
Cloud

Largest Data Center Companies Statistics 2026: Capacity and Revenue

AI Data Center Build-Out 2026: Projects, Power and GPUs - ai data centers
AI

AI Data Center Statistics 2026: Build-Out Projects, Power and GPUs

Disclaimer: Tricity Local News publishes figures and reporting for general information only. Nothing on this site is investment or legal advice, and no figure is a promise about a product’s uptime, cost or security. Check the cited source and its date before you rely on a number for a decision.

Primary Sidebar

Trending Topics

  • AI
  • Cloud
  • Data
  • Enterprise IT
  • News

Table of Contents

  • Key Takeaways
  • Editor’s Choice
  • Data Center Construction Spending by Month
  • About This Data
  • How much is being spent on data center construction?
  • Annual Data Center Construction Spending, 2022 to 2025
  • Recent Developments
  • Data Center vs Office and Nonresidential Construction
  • What Census Data Center Construction Spending Counts
  • Does Census data center spending include servers?
  • Data Center Construction Cost per MW
  • How much does it cost to build a data center per MW?
  • Data Center Construction Cost per Watt by Market
  • Data Center Capacity Under Construction in North America
  • How many megawatts of data centers are under construction?
  • Who Data Centers Are Being Built For
  • Data Center Construction Delays and Power Constraints
  • Why are data center construction projects delayed?
  • Data Center Construction Financing
  • Is data center construction slowing down?
  • Conclusion

Footer

Editorial & Trust

  • About
  • Press
  • Publishing Principles
  • Fact-Check Policy
  • Corrections Policy
  • Ethics Policy
  • Disclaimer
  • Cookie Policy

Key Topics

  • Data Center Stats
  • AI Data Center Stats
  • AI Capex Stats
  • Cloud Computing Stats
  • Machine Learning Stats
  • Hyperscale Data Center Stats
  • eDiscovery Stats

Categories

  • AI
  • Cloud
  • Data
  • Enterprise IT
  • News
Contact Us

Copyright © 2025–2026 Tricity Local News. All Rights Reserved.

  • Privacy Policy
  • Terms
  • Accessibility Statement
Company
  • About Us
  • Our Team
  • Our Mission
  • Core Values
Discover
  • stats-icon
    Statistics
Categories
  • AI
  • Cloud
  • Enterprise IT
  • News
AI
AI Inference Cost Statistics 2026: Price per Token Trends
AI Inference Cost Statistics 2026: Price per Token Trends
GPU Market Share Statistics 2026: NVIDIA, AMD and H100 Prices
GPU Market Share Statistics 2026: NVIDIA, AMD and H100 Prices
AI Capex Statistics 2026: Hyperscaler Spending by Company
AI Capex Statistics 2026: Hyperscaler Spending by Company
AI Data Center Build-Out 2026: Projects, Power and GPUs - ai data centers
AI Data Center Statistics 2026: Build-Out Projects, Power and GPUs
Machine Learning Statistics
The Ultimate List of Machine Learning Statistics for 2026
Cloud
Cloud Market Share 2026: Largest Cloud Providers Ranked
Cloud Market Share Statistics 2026: Largest Cloud Providers Ranked
Largest Data Centers in the US 2026: Sites, States and Capacity
Largest Data Centers in the US Statistics 2026: Sites and Capacity
Data Center Jobs and Economic Impact Statistics 2026
How Many Jobs Do Data Centers Create? Statistics 2026: Jobs per Site
Data Center Water Usage Statistics 2026
Data Center Water Usage Statistics 2026: Campus and AI Water Use
Hyperscale Data Center Statistics 2026: Count, Capacity and Spend - hyperscale data centers
Hyperscale Data Center Statistics 2026: Count, Capacity and Spend
Data Center Construction Statistics 2026: Costs, Pipeline and Delays
Data Center Construction Statistics 2026: Costs, Pipeline and Delays
Enterprise IT
DevOps Statistics DORA Metrics AI Adoption and Developer Pay
DevOps Statistics 2026: DORA Metrics, AI Adoption and Developer Pay
Cell Phones At Workplace Statistics
Top Cell Phones At Workplace Statistics and Trends Shaping 2026
eDiscovery Statistics
eDiscovery Statistics: You Need to Know in 2026
News
Netflix 2026 Q2 Revenue
Netflix Q2 2026 Revenue Nears $12.56 Billion Estimate, but Weak Guidance Sends Shares Down 9%
Categories
  • AI
  • Cloud
  • Enterprise IT
  • News
AI
AI Inference Cost Statistics 2026: Price per Token Trends
AI Inference Cost Statistics 2026: Price per Token Trends
GPU Market Share Statistics 2026: NVIDIA, AMD and H100 Prices
GPU Market Share Statistics 2026: NVIDIA, AMD and H100 Prices
AI Capex Statistics 2026: Hyperscaler Spending by Company
AI Capex Statistics 2026: Hyperscaler Spending by Company
AI Data Center Build-Out 2026: Projects, Power and GPUs - ai data centers
AI Data Center Statistics 2026: Build-Out Projects, Power and GPUs
Machine Learning Statistics
The Ultimate List of Machine Learning Statistics for 2026
Cloud
Cloud Market Share 2026: Largest Cloud Providers Ranked
Cloud Market Share Statistics 2026: Largest Cloud Providers Ranked
Largest Data Centers in the US 2026: Sites, States and Capacity
Largest Data Centers in the US Statistics 2026: Sites and Capacity
Data Center Jobs and Economic Impact Statistics 2026
How Many Jobs Do Data Centers Create? Statistics 2026: Jobs per Site
Data Center Water Usage Statistics 2026
Data Center Water Usage Statistics 2026: Campus and AI Water Use
Hyperscale Data Center Statistics 2026: Count, Capacity and Spend - hyperscale data centers
Hyperscale Data Center Statistics 2026: Count, Capacity and Spend
Data Center Construction Statistics 2026: Costs, Pipeline and Delays
Data Center Construction Statistics 2026: Costs, Pipeline and Delays
Enterprise IT
DevOps Statistics DORA Metrics AI Adoption and Developer Pay
DevOps Statistics 2026: DORA Metrics, AI Adoption and Developer Pay
Cell Phones At Workplace Statistics
Top Cell Phones At Workplace Statistics and Trends Shaping 2026
eDiscovery Statistics
eDiscovery Statistics: You Need to Know in 2026
News
Netflix 2026 Q2 Revenue
Netflix Q2 2026 Revenue Nears $12.56 Billion Estimate, but Weak Guidance Sends Shares Down 9%
Envelope holding a monthly statistics report with a rising chart

Tech numbers, once a month

One short briefing a month. Every figure links to its source.

One email a month. Unsubscribe anytime.